2021-04-21

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
  3. To join via phone, use one of the following numbers and the Conference ID: 946721076.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Rough timetable:

  1. CMTF tests with C75-1 (late-March - early-June).
  2. UITF beamline Modification in parallel to install new beamline
  3. Supplementary Shielding Installation: Mid-June
  4. Beamline Commissioning / Test Plans / Shielding Verification
  5. 7/26/21 Start Hot Check-out
  6. Commission new beam line and execute experiment [May slide a week... and weekends also available if desired]

Long Term Schedule (McCaughan) Strawman

New items for discussion:

  • Beam Studies updates
  • Short term schedule update:
    1. This week:
      • HDIce start breaking down shield wall w/ Hall B techs (Completed)
      • Talk w/ RCG about lead removal from 6D (Completed)
      • HDIce control room breakdown for High-B space take over (Completed)
      • Manual valves in downstream of booster and in elevated line closed (Completed)
      • 80/20 cleaned off for installation; lead stored
      • Gun work begins (Survey work started)
    2. Next Week:
      • Component disconnects (All but part of EES-IC this week; remaining early next week)
      • Stage larger table for beamline prep behind MeV dump
      • Vent elevated line for component removal
      • Pull components from elevated line
      • Diagnose Chopper slit
      • Pull Heliax from Sprectrum analyzer/Control room >> Buncher
      • Need Al base plate for FC3 region rework
      • Build 80/20 support structure; add mounting plates/brackets/etc.
      • Inventory Faye's old office for materials
  • Engineering
  • Other business

Reports on Open Action Items:

  • Action Items:
    1. Formal run plan