2021-05-26

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
  3. To join via phone, use one of the following numbers and the Conference ID: 946721076.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Long Term Schedule: Gantt (Outstanding tasks)

  1. Supplementary Shielding Installation: Mid-June
  2. Beamline Commissioning / Test Plans / Shielding Verification
  3. 7/26/21 Start Hot Check-out
  4. Commission new beam line and execute experiment
  5. Science!!!

New items for discussion:

Short term schedule update:
This week:

  • Area up to transition after solenoid under vacuum. RGA leak check completed.
  • Downstream viewer / faraday cup assembly under vacuum. RGA leak check completed.
  • One 4 5/8" BPM failed insertion checks, second 4 5/8" BPM stolen from elevated line has stripped hole (re-tap later), 3rd one removed and installed.
  • Spool pieces installed on both sides of 1st cross (one last one remaining); all but ~2 feet of beam line now under vacuum and leak checked.
  • Roof tiles off for HDIce (5/24), Dilution refrigerator craned out (5/25), and then roof tiles replaced again (5/26).
  • Last spool piece under fabrication.
  • Gun work progressing well:
    1. HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again.
    2. Gun rebuild schedule
    3. Minor SF6 leak in HV chamber identified; repair later...


Next Week:

  • Mount bottle rack in Labyrinth; remove gas bottles to rack.
  • Wastewater experiment line fully under vacuum (with flange in place of the thin window).
  • Install target mechanism
  • Build 80/20 support structure; Pb table components awaiting delivery.
  • Unistrut mounting for cables - Neal will do when available
  • Break vacuum in FC3 region
  • Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.


2 weeks:

  • Add Mu metal over bellows on wastewater line.
  • Switch Wastewater line Vacuum HV from local supplies to house power. Make UED updates as appropriate for vacuum system.
  • Pull Heliax from Spectrum analyzer/Control room >> Buncher
  • 4th terminal system in Control room under assembly/rebuild
  • Items from To-do list...

Engineering Other business

Reports on Open Action Items:

Action Items:

  • Formal run plan (McCaughan)