Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
  3. To join via phone, use one of the following numbers and the Conference ID: 946721076.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Long Term Schedule: Gantt (Outstanding tasks)

  1. Supplementary Shielding Installation: Mid-June
  2. Beamline Commissioning / Test Plans / Shielding Verification
  3. 7/26/21 Start Hot Check-out
  4. Commission new beam line and execute experiment
  5. Science!!!

New items for discussion:

Short term schedule update:
This week:

  • Elevated beam line terminated in pump and RGA leak checked
  • Experimental beam line under vacuum with thin window attached, RGA leak check required.
  • Vacuum pumping down well, but light bake may be required once we have completed installation.
  • STAC5 controller for chopper configured, installed, and tested.
  • FC3 region vented, purged, and mostly reconfigured.
  • Go ahead given by division management for FML to procure concrete shielding using funds from LDRD and UITF (10K+30kprocurement+30K AIP/Labor reapportionment)

Still to do:

  • Finish FC3 region vacuum work.
  • Install target mechanism
  • Add Mu metal over bellows on wastewater line.
  • EES may start cabling downstream section & making UED updates.


Next Week:

  • Build 80/20 support structure; Pb table components awaiting delivery. (status update?)
  • Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
  • Mount bottle rack in Labyrinth; remove gas bottles to rack.
  • Unistrut mounting for cables - Neal will do when available


2 weeks:

  • Pull Heliax from Spectrum analyzer/Control room >> Buncher
  • 4th terminal system in Control room under assembly/rebuild
  • Items from To-do list...

Engineering Other business

Reports on Open Action Items:

Action Items:

  • Formal run plan (McCaughan)