2021-07-21

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
  3. To join via phone, use one of the following numbers and the Conference ID: 984025598.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Long Term Schedule: Gantt (Outstanding tasks)

  1. 7/26/21 Start Hot Check-out


New items for discussion:

Short term schedule update:
This week:

Reports by Group: CIS/EGG:

DC Power:

    1. Corrector installation & cable reroute mostly complete, turned over to DC power
    2. Correctors inventoried following some naming confusion (MHB vs MBH); MBH = Magnet Big Haimson (2.75" bore); MHB family will be renamed MLH = Magnet Little Haimson (1.5" bore)
    3. Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets
    4. Raster installation - completed; per Bill Gunning. (Thanks!) Also, thank you for software and channel access integration by Weiwei & Brian and John for staying on top of things!
    5. Solenoid PS being installed

Instrumentation and Controls:

RF:

    1. 6GHz > 1.5GHz Down-converter installed for bunch length system

Vacuum:

SSG:

    1. BLM locations being set 7/21 following this meeting
    2. FSD inputs for magnet and BCM being prepared

ME / Installation:

    1. Nomenclature for elements disseminated and labelled
    2. Build 80/20 support structure for Pb (Completed)
    3. Ready to install Al base plates for FC3 region rework as well as solenoid stand. 80/20 reworked for support
    4. Pb stacked; RCG required modification due to permanent shielding req delay.
    5. New designs for FC3 and FC4 with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction!
    6. Songsheet being updated by Shaun; be sure to let him know when changes are made!

Experiment:

    1. ESAD, COO, and draft response to ERR under way by Gigi. ESAD/COO signed and turned over to Accelerator DSO.

Other:



Still to do:

  • Add Mu metal over bellows on wastewater line.


Next Week:

  • Mount bottle rack in Labyrinth (Staged); remove gas bottles to rack.
  • Unistrut mounting for cables - Neal will do when available
  • Engineering work on beam line starting

2 weeks:

  • Pull Heliax from Spectrum analyzer/Control room >> Buncher
  • 4th terminal system in Control room under assembly/rebuild
  • Items from To-do list...

Engineering Other business

Reports on Open Action Items:

Action Items:

Back to Main Meeting Minutes Page