Injector Quick Reference

Phase 1 - CED Info

Phase 1 - ME Songsheets

Phase 1 - ME Released Drawings

  • SECTION 1 => M:\me-group\2020 INJECTOR BEAMLINE\2020 Injector Beamline Arrangements\JL0091130-0100, SECTION 01\00-RELEASED DRAWINGS
  • SECTION 2 => M:\me-group\2020 INJECTOR BEAMLINE\2020 Injector Beamline Arrangements\JL0091130-0200, SECTION 02\00-RELEASED DRAWINGS
  • SECTION 3 => M:\me-group\2020 INJECTOR BEAMLINE\2020 Injector Beamline Arrangements\JL0091130-0300, SECTION 03\00-RELEASED DRAWINGS

Phase 1 - ME Design Layouts

Phase 2 - ME Design Layouts

Note: At the November 12, 2019 Modeling meeting [1], we decided to move the buncher to the midpoint position (between the centerline of the choppers and the centerline of the 2-cell in the booster). The buncher position in the July 2019 layout drawings is not the midpoint position; the buncher is shifted closer to the choppers in the July 2019 layout drawings.

-QCM was .32" further downstream. so all those interfaces moved.
-distance between chopper cavities was 59.32", so distance from center of choppers to downstream face of chopper #2 increased from 29.65" to 29.66".
-buncher, IFY0I06, MB00I06, A3, YAO cavity, A4 all moved slightly downstream.
-YAO cavity was .37" longer than the design drawing.

Overall Phase 1 & 2 - ME Design Layouts

Note: At the November 12, 2019 Modeling meeting [2], we decided to move the buncher to the midpoint position (between the centerline of the choppers and the centerline of the 2-cell in the booster). The buncher position in the July 2019 layout drawings is not the midpoint position; the buncher is shifted closer to the choppers in the July 2019 layout drawings.