;COVID Plan (Present)
+
; Post COVID Injector Upgrade Installation Plan
: Phase 1 (8/26/20) - [[media:200826_AIPINJ_Schedule.xlsx]]
+
* Phase 1 (Sep 2020 -  Jul 2021)
: Run (Jun'21 - Sep'21)
+
:: [https://www.jlab.org/news/stories/remote-working-team-tame-electron-beams-0 Remote working article]
: Phase 2 (Oct'21 - Feb'22)
+
* CEBAF Run (Aug 2021 - Dec 2021)
 +
* Phase 2 (Jan 2022 - Mar 2022)
  
; Pre-COVID Plan (Outdated)
+
; Pre COVID Injector Upgrade Installation Plan
: Phase 1 (May 6 - end of 2020)
+
* Phase 1 (May 6 2020 - Dec 2020)
: Run (Jan 2021 - Sep 13 2021)
+
* CEBAF Run (Jan 2021 - Sep 2021)
: Phase 2 (Sep 13 - end of 2021)
+
* Phase 2 (Sep 2021 - Dec 2021)

Latest revision as of 14:59, 13 February 2021

Post COVID Injector Upgrade Installation Plan
  • Phase 1 (Sep 2020 - Jul 2021)
Remote working article
  • CEBAF Run (Aug 2021 - Dec 2021)
  • Phase 2 (Jan 2022 - Mar 2022)
Pre COVID Injector Upgrade Installation Plan
  • Phase 1 (May 6 2020 - Dec 2020)
  • CEBAF Run (Jan 2021 - Sep 2021)
  • Phase 2 (Sep 2021 - Dec 2021)