; Injector Upgrade Plan (updated post COVID)
+
; Post COVID Injector Upgrade Installation Plan
* Phase 1 (Sep 2020 -  Jun 2021) - Updated 10/9/20 [[media:201008_AIPINJ_Schedule.xlsx]]
+
* Phase 1 (Sep 2020 -  Jul 2021)
* CEBAF Run (Jul? 2021 - Sep 2021)
+
:: [https://www.jlab.org/news/stories/remote-working-team-tame-electron-beams-0 Remote working article]
* Phase 2 (Oct 2021 - Feb 2022)
+
* CEBAF Run (Aug 2021 - Dec 2021)
 +
* Phase 2 (Jan 2022 - Mar 2022)
  
; Injector Upgrade Plan (original pre COVID)
+
; Pre COVID Injector Upgrade Installation Plan
 
* Phase 1 (May 6 2020 - Dec 2020)
 
* Phase 1 (May 6 2020 - Dec 2020)
 
* CEBAF Run (Jan 2021 - Sep 2021)
 
* CEBAF Run (Jan 2021 - Sep 2021)
 
* Phase 2 (Sep 2021 - Dec 2021)
 
* Phase 2 (Sep 2021 - Dec 2021)

Latest revision as of 14:59, 13 February 2021

Post COVID Injector Upgrade Installation Plan
  • Phase 1 (Sep 2020 - Jul 2021)
Remote working article
  • CEBAF Run (Aug 2021 - Dec 2021)
  • Phase 2 (Jan 2022 - Mar 2022)
Pre COVID Injector Upgrade Installation Plan
  • Phase 1 (May 6 2020 - Dec 2020)
  • CEBAF Run (Jan 2021 - Sep 2021)
  • Phase 2 (Sep 2021 - Dec 2021)