; Injector Upgrade Plan (original pre COVID) | ; Injector Upgrade Plan (original pre COVID) | ||
− | * Phase 1 (May 6 - | + | * Phase 1 (May 6 2020 - Dec 2020) |
− | * Run (Jan 2021 - Sep | + | * CEBAF Run (Jan 2021 - Sep 2021) |
− | * Phase 2 (Sep | + | * Phase 2 (Sep 2021 - Dec 2021) |
Revision as of 17:39, 9 October 2020
- Injector Upgrade Plan (updated post COVID)
- Phase 1 (Sep 2020 - Jun 2021) - Updated 10/9/20 media:201008_AIPINJ_Schedule.xlsx
- CEBAF Run (Jul? 2021 - Sep 2021)
- Phase 2 (Oct 2021 - Feb 2022)
- Injector Upgrade Plan (original pre COVID)
- Phase 1 (May 6 2020 - Dec 2020)
- CEBAF Run (Jan 2021 - Sep 2021)
- Phase 2 (Sep 2021 - Dec 2021)