(Created page with "==Agenda== '''Critical path action items''' # Define if anode tube will be permanently at ground, or will be electrically isolated by April 13 # Verify HV chamber dimensions...")
 
Line 2: Line 2:
  
 
'''Critical path action items'''
 
'''Critical path action items'''
# Define if anode tube will be permanently at ground, or will be electrically isolated by April 13
+
# Let's make two version of  anode tube:
 +
#* One version will be permanently at ground
 +
#* The second version will be electrically isolated
 +
# The anode DS flange design will be based on the flange design from Injector Phase 1 (drawing ending in 0101, see below)
 
# Verify HV chamber dimensions
 
# Verify HV chamber dimensions
 
#*Shaun: is this needed for defining anode tube length?
 
#*Shaun: is this needed for defining anode tube length?

Revision as of 09:33, 12 April 2022

Agenda

Critical path action items

  1. Let's make two version of anode tube:
    • One version will be permanently at ground
    • The second version will be electrically isolated
  2. The anode DS flange design will be based on the flange design from Injector Phase 1 (drawing ending in 0101, see below)
  3. Verify HV chamber dimensions
    • Shaun: is this needed for defining anode tube length?
    • Do you have HV chamber prints from Lekser?
    • Do you need S&A to measure HV chamber?
  4. Marcy, what are your conclusions on the HV chamber vacuum?
  5. Layout for CEBAF installation
    • The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101, see below). It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.
    • Anode flange prints and pictures