'''Critical path action items'''
 
'''Critical path action items'''
 
# Let's make two version of  anode tube:
 
# Let's make two version of  anode tube:
#* One version will be permanently at ground
+
#* One version will be permanently at ground (no Macor spacer, longer tube to make up spacer length 0.25 inches)
#* The second version will be electrically isolated
+
#* The second version will be electrically isolated as originally planned with Macor spacer and ceramic bushings
# The anode DS flange design will be based on the flange design from Injector Phase 1 (drawing ending in 0101, see below)
+
# The anode DS flange design will be based on the flange design from Injector Phase 1 (drawing ending in 0101, see below), but with two feedthrough ports.
 +
#*Marcy, Joe mentioned installing this flange in the injector was a challenge: the ports gets in the way for assembly? How would having two ports affect this? Is there a better way to place them? See pictures below.
 
# Verify HV chamber dimensions
 
# Verify HV chamber dimensions
 
#*Shaun: is this needed for defining anode tube length?
 
#*Shaun: is this needed for defining anode tube length?
#*Do you have HV chamber prints from Lekser?  
+
#*Do you have HV chamber prints from Lesker?  
 
#*Do you need S&A to measure HV chamber?
 
#*Do you need S&A to measure HV chamber?
# Marcy, what are your conclusions on the HV chamber vacuum?
+
# Vacuum,
 +
#*Marcy, what are your conclusions on the HV chamber vacuum?
 +
#*Do you have all the measurements for Shaun to start the NEG drawings?  
 
# Layout for CEBAF installation
 
# Layout for CEBAF installation
 
#*The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101, see below). It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.
 
#*The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101, see below). It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.
#* [[Anode flange prints and pictures]]
 
  
 +
'''Useful documents'''
 +
* [[Anode flange prints and pictures]]
 +
*[[Media:CIS-ASY-R30-3 schedule updateed April 12 2022.xlsx]]
 +
*[[Media:14" HV chamber CEBAF injector vacuum piping dimensions.pptx]]
  
*[https://jlab-org.zoomgov.com/j/1605572674?pwd=ZW11cHUvRXUwM1hpMTRBT3Fxb2dUQT09 zoom meeting link]
+
'''Updates'''
**Meeting ID: 160 557 2674
+
* C. Would has talked to Shaun about doing "as founds" on the HV chamber.
**Passcode: 471792
+
* Marcy reports that she is nearing the collection data and expect to have the HV chamber ready for venting by the end of this week
 +
 
 +
 
 +
*[https://jlab-org.zoomgov.com/j/16121791631 zoom meeting link]
 +
*Meeting ID: 161 2179 1631
  
 
* [https://wiki.jlab.org/ciswiki/index.php/Update_meetings Back to Update Meetings]
 
* [https://wiki.jlab.org/ciswiki/index.php/Update_meetings Back to Update Meetings]

Latest revision as of 08:58, 13 April 2022

Agenda

Critical path action items

  1. Let's make two version of anode tube:
    • One version will be permanently at ground (no Macor spacer, longer tube to make up spacer length 0.25 inches)
    • The second version will be electrically isolated as originally planned with Macor spacer and ceramic bushings
  2. The anode DS flange design will be based on the flange design from Injector Phase 1 (drawing ending in 0101, see below), but with two feedthrough ports.
    • Marcy, Joe mentioned installing this flange in the injector was a challenge: the ports gets in the way for assembly? How would having two ports affect this? Is there a better way to place them? See pictures below.
  3. Verify HV chamber dimensions
    • Shaun: is this needed for defining anode tube length?
    • Do you have HV chamber prints from Lesker?
    • Do you need S&A to measure HV chamber?
  4. Vacuum,
    • Marcy, what are your conclusions on the HV chamber vacuum?
    • Do you have all the measurements for Shaun to start the NEG drawings?
  5. Layout for CEBAF installation
    • The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101, see below). It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.

Useful documents

Updates

  • C. Would has talked to Shaun about doing "as founds" on the HV chamber.
  • Marcy reports that she is nearing the collection data and expect to have the HV chamber ready for venting by the end of this week