April 13, 2022 - HV chamber layout for installation in CEBAF
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Agenda
Critical path action items
- Let's make two version of anode tube:
- One version will be permanently at ground
- The second version will be electrically isolated
- The anode DS flange design will be based on the flange design from Injector Phase 1 (drawing ending in 0101, see below)
- Verify HV chamber dimensions
- Shaun: is this needed for defining anode tube length?
- Do you have HV chamber prints from Lekser?
- Do you need S&A to measure HV chamber?
- Marcy, what are your conclusions on the HV chamber vacuum?
- Layout for CEBAF installation
- The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101, see below). It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.
- Anode flange prints and pictures
- zoom meeting link
- Meeting ID: 160 557 2674
- Passcode: 471792