200kV Gun
- Opera/Tosca 3D Model
- Timeline/sequence for 200kV HV chamber media:170414_CHG.pdf
Machine Fit-up UHV clean Degas 900C (Carpenter) Barrel polish Second UHV clean S&A assembly + fiducial Bake in UITF w/ SLAC heater table/controls Radmon in UITF w/ FEL radmon + Sue Witherspoon software + John tubes High voltage in UITF w/ TOSP For diagnostics in EPICS: radmon + UHV + anode current + analog output of HVPS to ADC/voltmeter
Gun2 NEG Tube
- Danny updated NEG tube media:NEGTUBE_MARCH31.pdf
Gun3 Removal
- Week May 8 to remove/replace Gun3 ATLIS task
Eliminating Gun Switch Software
- Kyle building a new screen, tracking to be ready in May or June
Spellman HVPS update
- John/Brad can now talk to HVPS
Radmon update
- Omar will NOT be ready w/ new system => plan on borrowing from LERF (or GTS?)