April 14, 2017 - 200kV gun upgrade meeting

From Ciswikidb
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

200kV Gun

Machine
Fit-up
UHV clean
Degas 900C (Carpenter)
Barrel polish
Second UHV clean
S&A assembly + fiducial
Bake in UITF w/ SLAC heater table/controls
Radmon in UITF w/ FEL radmon + Sue Witherspoon software + John tubes
High voltage in UITF w/ TOSP
For diagnostics in EPICS:  radmon + UHV + anode current + analog output of HVPS to ADC/voltmeter

Gun2 NEG Tube

Gun3 Removal

Eliminating Gun Switch Software

  • Kyle building a new screen, tracking to be ready in May or June

Spellman HVPS update

  • John/Brad can now talk to HVPS

Radmon update

  • Omar will NOT be ready w/ new system => plan on borrowing from LERF (or GTS?)

SAD Schedule