Agenda

Critical path action items

  1. Anode flange designed based on Injector Phase 1 but with two HV ports
    • Need to order:
      • 2 two zero length reducer 10" to 4-1/2" flanges
      • 4 weldable 1-1/3" non-rotatable tapped flanges, or already welded to tube. Shaun?
      • 4 10 kV SHV feedthroughs. (Marcy, do we have these?, how many?)
      • Ceramic beads
      • Carlos to look for alternative to Cu wire with lower coefficient of expansion
  2. Screen Design
  3. Define layout for installation in CEBAF injector