Difference between revisions of "April 21, 2022 - HV chamber layout for installation in CEBAF"

From Ciswikidb
Jump to navigation Jump to search
Line 11: Line 11:
 
# Screen Design
 
# Screen Design
 
#*Marcy dimension requests [[media:screens18gun.pptx]]
 
#*Marcy dimension requests [[media:screens18gun.pptx]]
 
+
# Define layout for installation in CEBAF injector
 +
#*The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101).
 +
#*It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.
 +
#**[[Media:14" HV chamber CEBAF injector vacuum piping dimensions.pptx]]
  
 
'''Useful documents'''
 
'''Useful documents'''
 
* [[Anode flange prints and pictures]]
 
* [[Anode flange prints and pictures]]
 
*[[Media:CIS-ASY-R30-3 schedule updateed April 12 2022.xlsx]]
 
*[[Media:CIS-ASY-R30-3 schedule updateed April 12 2022.xlsx]]
*[[Media:14" HV chamber CEBAF injector vacuum piping dimensions.pptx]]
+
 
  
 
'''Updates'''
 
'''Updates'''

Revision as of 07:39, 21 April 2022

Agenda

Critical path action items

  1. Anode flange designed based on Injector Phase 1 but with two HV ports
    • Need to order:
      • 2 two zero length reducer 10" to 4-1/2" flanges
      • 4 weldable 1-1/3" non-rotatable tapped flanges, or already welded to tube. Shaun?
      • 4 10 kV SHV feedthroughs. (Marcy, do we have these?, how many?)
      • Ceramic beads
      • Carlos to look for alternative to Cu wire with lower coefficient of expansion
  2. Screen Design
  3. Define layout for installation in CEBAF injector

Useful documents


Updates