Difference between revisions of "April 21, 2022 - HV chamber layout for installation in CEBAF"
Jump to navigation
Jump to search
(Created page with "== Screen Design == Marcy dimension requests screens18gun.pptx") |
|||
(7 intermediate revisions by 2 users not shown) | |||
Line 1: | Line 1: | ||
− | == | + | ==Agenda== |
− | Marcy dimension requests [[screens18gun.pptx]] | + | '''Critical path action items''' |
+ | # Anode flange designed based on Injector Phase 1 but with two HV ports | ||
+ | #* Need to order: | ||
+ | #**2 two zero length reducer 10" to 4-1/2" flanges | ||
+ | #**4 weldable 1-1/3" non-rotatable tapped flanges, or already welded to tube. Shaun? | ||
+ | #**4 10 kV SHV feedthroughs. (Marcy, do we have these?, how many?) | ||
+ | #** Ceramic beads | ||
+ | #** Carlos to look for alternative to Cu wire with lower coefficient of expansion | ||
+ | # Screen Design | ||
+ | #*Marcy dimension requests [[media:screens18gun.pptx]] | ||
+ | # Define layout for installation in CEBAF injector | ||
+ | #*The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101). | ||
+ | #*It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed. | ||
+ | #*[[Media:14" HV chamber CEBAF injector vacuum piping dimensions.pptx]] | ||
+ | |||
+ | '''Useful documents''' | ||
+ | * [[Anode flange prints and pictures]] | ||
+ | *[[Media:CIS-ASY-R30-3 schedule updateed April 12 2022.xlsx]] | ||
+ | |||
+ | |||
+ | '''Updates''' | ||
+ | * | ||
+ | |||
+ | '''TEAMS meeting link sent along with invite''' | ||
+ | |||
+ | * [https://wiki.jlab.org/ciswiki/index.php/Update_meetings Back to Update Meetings] |
Latest revision as of 07:39, 21 April 2022
Agenda
Critical path action items
- Anode flange designed based on Injector Phase 1 but with two HV ports
- Need to order:
- 2 two zero length reducer 10" to 4-1/2" flanges
- 4 weldable 1-1/3" non-rotatable tapped flanges, or already welded to tube. Shaun?
- 4 10 kV SHV feedthroughs. (Marcy, do we have these?, how many?)
- Ceramic beads
- Carlos to look for alternative to Cu wire with lower coefficient of expansion
- Need to order:
- Screen Design
- Marcy dimension requests media:screens18gun.pptx
- Define layout for installation in CEBAF injector
- The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101).
- It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.
- Media:14" HV chamber CEBAF injector vacuum piping dimensions.pptx
Useful documents
Updates
TEAMS meeting link sent along with invite