April 21, 2022 - HV chamber layout for installation in CEBAF
Jump to navigation
Jump to search
Agenda
Critical path action items
- Anode flange designed based on Injector Phase 1 but with two HV ports
- Need to order:
- 2 two zero length reducer 10" to 4-1/2" flanges
- 4 weldable 1-1/3" non-rotatable tapped flanges, or already welded to tube. Shaun?
- 4 10 kV SHV feedthroughs. (Marcy, do we have these?, how many?)
- Ceramic beads
- Carlos to look for alternative to Cu wire with lower coefficient of expansion
- Need to order:
- Screen Design
- Marcy dimension requests media:screens18gun.pptx
- Define layout for installation in CEBAF injector
- The plan is to focus on layout for installing in CEBAF using DS anode flange design from Injector Phase 1 (drawing ending in 0101).
- It is critical to define this flange by the end of April so that it can be fabricated, and vacuum degassed.
Useful documents
Updates
TEAMS meeting link sent along with invite