Difference between revisions of "April 26, 2022 - updates"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "==Agenda== '''Updates''' # Anode flange designed based on Injector Phase 1 but with two HV ports #* Bubba i placing the order for: #*2 one zero length reducer 10" to 4-1/2" f...")
 
Line 9: Line 9:
 
#* Ceramic beads are on hand
 
#* Ceramic beads are on hand
 
#*Shaun submitted anode part fab request to shop (Vine says it will take ~2 weeks to complete)
 
#*Shaun submitted anode part fab request to shop (Vine says it will take ~2 weeks to complete)
#** Carlos to look for alternative to Cu wire with lower coefficient of expansion
+
#* Carlos to look for alternative to Cu wire with lower coefficient of expansion
 
# Screen Design
 
# Screen Design
 
#*Shaun is finalizing screen design
 
#*Shaun is finalizing screen design

Revision as of 09:04, 26 April 2022

Agenda

Updates

  1. Anode flange designed based on Injector Phase 1 but with two HV ports
    • Bubba i placing the order for:
    • 2 one zero length reducer 10" to 4-1/2" flanges, 304 SSS in stock, and one 316 L SS 3 month delivery
    • 4 weldable 1-1/3" non-rotatable tapped flanges, or already welded to tube. Shaun?
    • Marcy has 3 of the 10 kV SHV feedthroughs.
    • Ceramic beads are on hand
    • Shaun submitted anode part fab request to shop (Vine says it will take ~2 weeks to complete)
    • Carlos to look for alternative to Cu wire with lower coefficient of expansion
  2. Screen Design
    • Shaun is finalizing screen design
    • Bubba ordered more weaved wire mesh that Marcy prefers: 0.88 mm wire diameter, 0.5 inch square opening
    • Bubba cut sample pieces of both thin and thick wire mesh. It looks like either will work fine, but we will make mockups with each type of mesh as soon was Shaun finalizes design
  3. Define layout for installation in CEBAF injector

Useful documents


Updates

TEAMS meeting link sent along with invite