April 6, 2016 - Monthly 4-laser Upgrade Status Meeting
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
We will meet Wed April 6 @ 11am in TL-1227 for monthly status update.
Schedule (Joe)
- Summer SAD
- Apr 06 - Apr 27 : Halls A/B/D
- Apr 27 - May 13 : Mini-down for Open House, PSS Cert : Install new RTP driver on Hall A laser for testing
- May 13 - Jun 27 : PRAD / Bubble runs
- Jun 27 – July 25 : Summer SAD 4-Laser Phase I : Laser Table, SCAM, PSS, Beam Tests
- Jul 26 – Aug 19 : Summer SAD 4-Laser Phase II : Float, 4-LLRF
- Aug 19 - Sep 1 : Bubble Run II
- Sep 2 - 20 : PSS Cert
- Oct 1 : Fall Run Begins
Laser Status (John)
- Status
SCAM-II (Roger)
- March
- Additional input from Kevin Jordan and Michael Tiefenback collected.
- Grames met with Injector group, solicited pre-draft input
- March 31st - Version 1 draft circulated media:SAMII_v1.docx to Flood, Hansknecht, Robertson, Higgins
- April
- Hansknecht and Robertson provided feedback
- Flood/Grames reviewed feedback and refined document punch list
- April 5th - Version 2 draft media:SAMII_v2.docx circulated to larger group for review
LLRF (Tomasz)
- Grames met with Injector group, verified there are no bunch length hooks into LLRF, use phase shifters
- March 14 - Draft of source requirements circulated media:LLRF-Source_v1.docx
- Implementation timeline media:4Laser_LLRF_overview.ppt