Difference between revisions of "Aug 16, 2022 - Group meeting"
Jump to navigation
Jump to search
Line 22: | Line 22: | ||
* Student projects, how are each of them going? | * Student projects, how are each of them going? | ||
* PSS kicker test at UITF by end of year, depends on SSG | * PSS kicker test at UITF by end of year, depends on SSG | ||
+ | |||
+ | ===Action Items=== | ||
+ | * Riad - submit PR for Mott VME crate | ||
+ | * Joe - tally bleed through results Spring 2022 | ||
+ | * Shukui - test 12 Mhz beam generation at UITF, Max to test w/ beam | ||
+ | * Phil - build YAG/HARP on cross w/ top-hat and Shaun's longer nipple | ||
+ | * Carlos - complete assembly of gun at LERF end of August | ||
+ | * Marcy - test YAG resistance | ||
+ | * Riad - finish PV reviews | ||
+ | * Shukui - submit PR for beam profiler for UITF | ||
===Updates=== | ===Updates=== |
Latest revision as of 12:47, 16 August 2022
General
- FY22 PR deadline is Friday
- We'll meet next Tuesday at noon for lunch, Aziz will present
- Phase I SBIR (LOI 8/29, Deadline 10/11) Link is here
- HEPA install
Next couple months
- Must
- Repair 250/500 seed board, improve board swapping, build one spare chassis
- By ready for Kicker and Compton experiments by October
- Complete 200 kV HV chamber build at LERF, be ready to install UITF by November
- Build and demo a YAG/HARP cross for CEBAF
- Should
- Reach next step in 500 kV insulator test
- Develop plan for next TE011 run at GTS, w/ realistic and assigned jobs and schedule
- Load bulk sample to miniMott, demonstrate polarimeter functioning with any light source
- Papers (magnetized beam, PV paper review, biased anode draft)
- Second round of Mott measurements at UITF (forward detector, solenoid offset, remote HV PS/IHWP)
- Like
- Student projects, how are each of them going?
- PSS kicker test at UITF by end of year, depends on SSG
Action Items
- Riad - submit PR for Mott VME crate
- Joe - tally bleed through results Spring 2022
- Shukui - test 12 Mhz beam generation at UITF, Max to test w/ beam
- Phil - build YAG/HARP on cross w/ top-hat and Shaun's longer nipple
- Carlos - complete assembly of gun at LERF end of August
- Marcy - test YAG resistance
- Riad - finish PV reviews
- Shukui - submit PR for beam profiler for UITF
Updates
- Joe - I'll be attending PSTP 9/25-9/30 (e+ program at Jlab) and then ERL 10/2-10/5 (e- polarized high current)
- Phil
- Gabriel
- Max
- Mamun
- Shukui
- Carlos
- Riad