* By ready for Kicker and Compton experiments by October
 
* By ready for Kicker and Compton experiments by October
 
* Complete 200 kV HV chamber build at LERF, be ready to install UITF by November
 
* Complete 200 kV HV chamber build at LERF, be ready to install UITF by November
 +
* Build and demo a YAG/HARP cross for CEBAF
  
 
;Should
 
;Should
 +
* Load bulk sample to miniMott, demonstrate polarimeter functioning with any light source
 
* Develop plan for next TE011 run at GTS, w/ realistic and assigned jobs and schedule
 
* Develop plan for next TE011 run at GTS, w/ realistic and assigned jobs and schedule
 
* Papers (magnetized beam, PV paper review, biased anode draft)
 
* Papers (magnetized beam, PV paper review, biased anode draft)
+
* Second round of Mott measurements at UITF (forward detector, solenoid offset, remote HV PS/IHWP)
 +
 
 
;Like
 
;Like
 
* Student projects, how are each of them going?
 
* Student projects, how are each of them going?
 +
* PSS kicker test at UITF by end of year, depends on SSG
  
 
===Updates===
 
===Updates===

Revision as of 08:52, 16 August 2022

General

  • FY22 PR deadline is Friday
  • We'll meet next Tuesday at noon for lunch, Aziz will present
  • Phase I SBIR

Next couple months

Must
  • Repair 250/500 seed board, improve board swapping, build one spare chassis
  • By ready for Kicker and Compton experiments by October
  • Complete 200 kV HV chamber build at LERF, be ready to install UITF by November
  • Build and demo a YAG/HARP cross for CEBAF
Should
  • Load bulk sample to miniMott, demonstrate polarimeter functioning with any light source
  • Develop plan for next TE011 run at GTS, w/ realistic and assigned jobs and schedule
  • Papers (magnetized beam, PV paper review, biased anode draft)
  • Second round of Mott measurements at UITF (forward detector, solenoid offset, remote HV PS/IHWP)
Like
  • Student projects, how are each of them going?
  • PSS kicker test at UITF by end of year, depends on SSG

Updates

  • Joe - I'll be attending PSTP 9/25-9/30 (e+ program at Jlab) and then ERL 10/2-10/5 (e- polarized high current)
  • Phil
  • Gabriel
  • Max
  • Mamun
  • Shukui
  • Carlos
  • Riad