Difference between revisions of "Aug 26, 2020"

From Ciswikidb
Jump to navigation Jump to search
Line 21: Line 21:
 
;SAD/AIPINJ
 
;SAD/AIPINJ
 
* Preliminary layout rev. 4 complete [[media:SONGSHEET AUGUST 21 dm comments.pdf]]
 
* Preliminary layout rev. 4 complete [[media:SONGSHEET AUGUST 21 dm comments.pdf]]
* ME folders on M: contain complete drawings
+
* ME folders on M: contain complete drawings => will copy these occasionally to AIPINJ share folder
  
 
;Budgets
 
;Budgets
 
* Marcy - many thanks for RSR vacuum estimates
 
* Marcy - many thanks for RSR vacuum estimates

Revision as of 15:39, 25 August 2020

News
CEBAF
  • Any news from on-call?
  • C goes to 1-pass for few days next week (Aug 31 - Sep 3) then returns
LERF
UITF
  • Lock-up Thu/Fri for SRF Booster testing
  • Matt is planning for Run 1 to begin on Mon Aug 31
Safety
  • Cat 2 PPE gear ordered for Joe, Bubba, Carlos, Marcy, Riad => pick-up on Thursday (otherwise 2 week delivery time)
  • Cat 2 PPE size chart media:200825_CAT2PPE.jpg
SAD/AIPINJ
Budgets
  • Marcy - many thanks for RSR vacuum estimates