Booster LLRF test plan

From Ciswikidb
Revision as of 11:28, 16 December 2020 by Poelker (talk | contribs)
Jump to navigation Jump to search

UITF LLRF Test Plan

To Do Before Tests

  • Check LLRF Version in chassis?
  • Test equipment moved to UITF
  • GDR-FSD has been fixed

What signals are still not archived? Organ Harvester. Has it been tested? Save-restore seems to be working Slopes for calibrated signals … Look at the Mike’s commissioning data and tests Check tuner stalk mechanical configuration

Non-Beam Tests Optimize gains for both two and seven cell. Cross talk between two and seven cell cavity 4kHz spurs …27 degrees are they there? Microphonic backgrounds of both two and seven cell cavities HDIce compressors?? Are they operational? Measure mechanical cross talk between the two cavities Tuner motors vs. microphonics What is the frequency vs. pressure for both cavities Detune klystron measurement …look at slopes

New algorithm tests Load code Interlock verifications Test SEL, SELA, SELAP Resonance control is not available yet … Magnitude/Phase Gain and Optimization Waveforms available

Beam Tests Energy spread measurement Beam stability RF-Longitudinal transfer function (laser …seven cell) Bunch Length measurement … Coupler kick effects on the beam …