Line 10: Line 10:
  
 
1- Bubble Chamber at Open House: Jefferson Lab Open House is on Saturday April 30, 2016. There will be a Bubble Chamber display (poster).
 
1- Bubble Chamber at Open House: Jefferson Lab Open House is on Saturday April 30, 2016. There will be a Bubble Chamber display (poster).
: [[media:bubble_final_April2016.pdf]]
+
: [[media:bubble_OpenHouse__April2016.pdf]]
: [[media:bubble_final_April2016.pptx]]
+
: [[media:bubble_OpenHouse_April2016.pptx]]
  
 
2- New Test Run II Schedule (see: Addendum to October 2015 - June 2017 Experiment Schedule (20160324) [https://www.jlab.org/exp_prog/experiment_schedule/2015/11-13/ExpSchAdd_20160324.pdf])
 
2- New Test Run II Schedule (see: Addendum to October 2015 - June 2017 Experiment Schedule (20160324) [https://www.jlab.org/exp_prog/experiment_schedule/2015/11-13/ExpSchAdd_20160324.pdf])

Revision as of 16:33, 25 April 2016

We will meet in TL 2221 on Wednesday April 6 at 3:30 pm EST.

For those calling in we'll use the Blue Jeans [1] audio conference system.

Phone number: 1-888-240-2560
Meeting ID: 3528502673#
Meeting URL: http://bluejeans.com/3528502673


Agenda:

1- Bubble Chamber at Open House: Jefferson Lab Open House is on Saturday April 30, 2016. There will be a Bubble Chamber display (poster).

media:bubble_OpenHouse__April2016.pdf
media:bubble_OpenHouse_April2016.pptx

2- New Test Run II Schedule (see: Addendum to October 2015 - June 2017 Experiment Schedule (20160324) [2])

  1. Bubble Installation: May 5 – May 12, 2016: Day shift only
  2. Bubble Run:
    1. June 13 – June 21, 2016: Day shift only
    2. June 22 – June 30, 2016: Day + Swing + Owl shifts

3- Test Run III: Aug 19 – Sept 2, 2016

4- Approved Bubble Chamber TOSP expired on Dec 8, 2015. Need to re-submit a new one for approval with addendum of changes to chamber and 100 µA beam current.

5- Bubble Chamber work at ANL: media:Bubble_Chamber_Design_Progress_6_April_2016.pdf




Notes from this meeting:

  • Chamber will not be ready for June run, we are now aiming for August run.