Bubble Chamber Meeting Wednesday July 1, 2015

From Ciswikidb
Revision as of 08:50, 8 July 2015 by Suleiman (talk | contribs)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

We will meet in TL 2221 on Wednesday July 1 at 3:30 pm EST.

For those calling in we'll use the Blue Jeans [1] audio conference system.

Phone number: 1-888-240-2560
Meeting ID: 3528502673#
Meeting URL: http://bluejeans.com/3528502673


Agenda:

1- Bubble Chamber progress at Argonne




Notes from this meeting:


  • Bubble Chamber:
  1. Made the 27" stand for JLab Injector beamline
  2. Ready to start crating, expect to ship by mid-July
  3. Cannot yet ship N2O – needs JLab and Argonne approval
  4. Upon arrival at JLab at the end of July, move to Injector tunnel
  5. Brad will provide description of the shipment and handling instruction
  6. Brad will be at JLab August 3 – 12.


  • Safety Reviews:
  1. Started pressure system approval process
  2. Will need Electrical Review since we have 208 V custom-made electrical distribution box
  3. Need a TOSP with all the operational and safety procedures (fire, power loss, ...)
  4. List of fluids:
    1. Mercury: 150 mL
    2. Superheated Liquid (N2O or C2F6): 40 – 60 mL
    3. Hydraulic Fluid: 5 gal
    4. Silicone Oil for Chiller: 2 L


  • Cancelled shifts of beam scheduled for August except for swing shifts in second week


  1. Dan Moser is our OPS liaison
  2. Accelerator schedule after August 15 is being reworked.