Line 34: | Line 34: | ||
# Mercury we be installed in chamber at Argonne. | # Mercury we be installed in chamber at Argonne. | ||
# Brad arrives on August 3. Cool and pressurize with C<sub>2</sub>F<sub>6</sub>. Complete safety reviews. | # Brad arrives on August 3. Cool and pressurize with C<sub>2</sub>F<sub>6</sub>. Complete safety reviews. | ||
− | # Beam on chamber in the second week of August filled with C<sub>2</sub>F<sub>6</sub>. | + | # Beam on chamber in the second week of August filled with C<sub>2</sub>F<sub>6</sub>. Beam kinetic energy = 4.0 - 5.5 MeV. |
+ | # Remove C<sub>2</sub>F<sub>6</sub> and fill with N<sub>2</sub>O during the last two week on August. | ||
+ | # Beam on chamber in the first two weeks of September |
Revision as of 17:23, 3 June 2015
We will meet in TL 2221 on Wednesday June 3 at 3:30 pm EST.
For those calling in we'll use the Blue Jeans [1] audio conference system.
Phone number: 1-888-240-2560 Meeting ID: 3528502673# Meeting URL: http://bluejeans.com/3528502673
Agenda:
1- Bubble Chamber progress at Argonne
2- Detection features of new bubble chamber: media:Detection_features_new_bubble_chamber.pdf
Notes from this meeting:
- Bubble Chamber:
- Showed bubbles distribution from N2O with mercury as buffer liquid using PuC neutron source.
- Plan to measure temperature gradient across the glass cell.
- Regarding CO2: it is possible to suppress the 12C(γ,α)2α signal but 13C(γ,n)12C background will be significant - Not an option.
- Test chamber with C2F6 as the super heated liquid.
- Schedule:
- Reconfigure bubble chamber beamline in the first two weeks of July.
- Chamber arrives JLab in middle of July. Move to Injector. Install and align.
- Mercury we be installed in chamber at Argonne.
- Brad arrives on August 3. Cool and pressurize with C2F6. Complete safety reviews.
- Beam on chamber in the second week of August filled with C2F6. Beam kinetic energy = 4.0 - 5.5 MeV.
- Remove C2F6 and fill with N2O during the last two week on August.
- Beam on chamber in the first two weeks of September