Difference between revisions of "CEBAF Injector Upgrade"
Jump to navigation
Jump to search
Line 6: | Line 6: | ||
:: Run (Jan 2021 - Sep 13 2021) | :: Run (Jan 2021 - Sep 13 2021) | ||
:: Phase 2 (Sep 13 - end of 2021) | :: Phase 2 (Sep 13 - end of 2021) | ||
− | |||
=== [[Injector Upgrade Meetings]] === | === [[Injector Upgrade Meetings]] === |
Revision as of 13:26, 13 February 2020
This area is related to Injector Upgrade Meetings
Injector upgrade calendar
- Run (now - May 6)
- Phase 1 (May 6 - end of 2020)
- Run (Jan 2021 - Sep 13 2021)
- Phase 2 (Sep 13 - end of 2021)
Injector Upgrade Meetings
Link to AIPINJ OneDrive folder
AIPINJ Layouts
Components
ATLIS Tasks
AIPINJ
- Testing Wien HV Controls at UITF
- Accelerator network re-survey
- Remove and re-install BPM's Gun to chopper
- Install new IPM2I03
- Remove and calibrate current monitoring electronics
- Harp work
Non-AIPINJ
- New Gun2 loading chamber
- Placeholder for Tim Minga to test laser room smoke detector alarm to MCC/Guard