=== Week 2 (Sep 28 - Oct 4) === | === Week 2 (Sep 28 - Oct 4) === | ||
+ | |||
+ | ; Fri 9/25 - Mon 9/28 | ||
+ | * CIS Gun Jobs | ||
+ | : Wien electrode testing – 9am!!! | ||
+ | : Gun HVPS lockout - DONE | ||
+ | : Gun HV cable disconnect – DONE | ||
+ | : Remove PIG – Coordinate w/ Neil for convenient time | ||
+ | : Shukui - Laser outrigger table as-founds, remove components | ||
+ | : Scott - Remove yellow box | ||
+ | : Scott - Disconnect Decarad | ||
+ | |||
+ | ; Tue 9/29 – Fri 10/1 | ||
+ | * Daniel will coordinate system disconnects (Magnets, Diagnostics, PSS, RF) | ||
+ | * Remove suitcase | ||
=== Week 3 (Oct 5 - Oct 11) === | === Week 3 (Oct 5 - Oct 11) === |
Revision as of 08:57, 25 September 2020
Week 1 (Sep 21 - Sep 27)
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4)
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Tue 9/29 – Fri 10/1
- Daniel will coordinate system disconnects (Magnets, Diagnostics, PSS, RF)
- Remove suitcase
Week 3 (Oct 5 - Oct 11)
Week 4 (Oct 12 - Oct 18)
Week 5 (Oct 19 - Oct 25)
- Injector is now in restricted access all the time
- LOTO and system disconnects
Week X
- Vacuum jobs Options for gun through y-chamber