Line 16: Line 16:
 
: Scott - Disconnect Decarad
 
: Scott - Disconnect Decarad
  
; Tue 9/29 – Fri 10/1
+
; Monday 9/28 Tasks (updated 0915 9/28)
* Daniel will coordinate system disconnects (Magnets, Diagnostics, PSS, RF)
+
* Power down Wein system (Scott/Joe)
 +
* Power down and remove DecaRad system (Scott)
 +
* Return gun valve config to "normal" (Marcy)
 +
* Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
 +
* PSS Kickers and associated chassis removal (SSG)
 +
* Laser table disassembly (Shukui/Scott)
 +
 
 +
; Tuesday 9/29 Tasks (updated 1230 9/28)
 +
* Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
 +
* Disconnect aperture and cup signal cables (Pete) 5a
 +
* Disconnect rad probes (Melvin) 8a
 +
* Tunnel magnet disconnects (Diggs, Delk) 10a
 +
* Removal of old chopper amps from rack (Farrish)
 +
*
 +
 
 +
; Tue 9/29 – Fri 10/1 (updated 0915 9/28)
 +
; <u>'''Tunnel Work'''</u>
 +
 
 +
{| class="wikitable"
 +
|-
 +
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2
 +
|-
 +
| 4a - 8a ||  || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling || I&C || I&C 
 +
|-
 +
| 8a - 10a || CIS + SSG || RadCon: rad probes || RF: Prebuncher ||  ||
 +
|-
 +
| 10a - 12p || CIS + SSG || DC Power ||  ||  ||
 +
|-
 +
| 12p - 2p || CIS + SSG || DC Power || DC Power || DC Power ||
 +
|-
 +
| 2p - 4p || CIS + SSG || DC Power || 3p: Moser: Safety Warden checks  ||  ||
 +
|-
 +
| 4p - ?? ||  ||  ||  ||  ||
 +
|}
 +
 
 
* Remove suitcase
 
* Remove suitcase
 +
* EES-IC Disconnects 5a - 8a, Tues-Fri
 +
* RadCon probe disconnects, 8a - 10a, Tues
 +
* DC Power magnet disconnects, 10a - 4p Tues, 10a-noon Wed+Thur
 +
* Prebuncher disconnects, 8a - 10a, Wed
  
 
=== Week 3 (Oct 5 - Oct 11) ===
 
=== Week 3 (Oct 5 - Oct 11) ===
 +
* Vacuum disconnects
  
 
=== Week 4 (Oct 12 - Oct 18) ===
 
=== Week 4 (Oct 12 - Oct 18) ===

Revision as of 17:30, 28 September 2020

Week 1 (Sep 21 - Sep 27)

Week 2 (Sep 28 - Oct 4)

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tuesday 9/29 Tasks (updated 1230 9/28)
  • Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • Removal of old chopper amps from rack (Farrish)
Tue 9/29 – Fri 10/1 (updated 0915 9/28)
Tunnel Work
Time Mon 9/28 Tue 9/29 Wed 9/30 Thu 10/1 F 10/2
4a - 8a I&C; 5a: Francis: BPMs, Cups, Apertures I&C; 430a: Greenfield + Gonzales: vacuum labelling I&C I&C
8a - 10a CIS + SSG RadCon: rad probes RF: Prebuncher
10a - 12p CIS + SSG DC Power
12p - 2p CIS + SSG DC Power DC Power DC Power
2p - 4p CIS + SSG DC Power 3p: Moser: Safety Warden checks
4p - ??
  • Remove suitcase
  • EES-IC Disconnects 5a - 8a, Tues-Fri
  • RadCon probe disconnects, 8a - 10a, Tues
  • DC Power magnet disconnects, 10a - 4p Tues, 10a-noon Wed+Thur
  • Prebuncher disconnects, 8a - 10a, Wed

Week 3 (Oct 5 - Oct 11)

  • Vacuum disconnects

Week 4 (Oct 12 - Oct 18)

Week 5 (Oct 19 - Oct 25)

  • Injector is now in restricted access all the time
  • LOTO and system disconnects

Week X