− | === Week 1 (Sep 21 - Sep 27) === | + | =2020 Weeks 1 through 13 = |
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | == Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
* Updated schedule [[media:200914_AIPINJ_Weeks_Sep_18_update.docx]] | * Updated schedule [[media:200914_AIPINJ_Weeks_Sep_18_update.docx]] | ||
* High voltage test slides [[media:200902_HV_Plans.pptx]] | * High voltage test slides [[media:200902_HV_Plans.pptx]] | ||
* Gun and Wien tasks [[Media:High Voltage Work Gun2 & Wien filters.xlsx]] | * Gun and Wien tasks [[Media:High Voltage Work Gun2 & Wien filters.xlsx]] | ||
+ | </div> | ||
− | + | == Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects == | |
− | + | <div class="mw-collapsible mw-collapsed"> | |
; Fri 9/25 - Mon 9/28 | ; Fri 9/25 - Mon 9/28 | ||
* CIS Gun Jobs | * CIS Gun Jobs | ||
Line 34: | Line 39: | ||
* Document existing Wein cabling and power off PS (Scott) | * Document existing Wein cabling and power off PS (Scott) | ||
+ | ; Wednesday 9/30 Tasks (updated 0900 9/30) | ||
+ | * RF Prebuncher disconnects (Farrish) 6a | ||
+ | * Vacuum Component Labeling (Greenfield, Gonzales) 430a | ||
+ | * Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a | ||
+ | * Tiny magnet removals (Scott, Grames) 9a | ||
+ | * PSS Kicker Magnet removal (SSG) 9a | ||
+ | * Sample hold cables install, InjSB (Francis) | ||
+ | * Remaining PSS Interface chassis removal (SSG) | ||
+ | * Harp upgrade to PC104 (Dela Cruz) | ||
+ | * Moser transfers CCOC phone @1430, to reach moving forward x5089 | ||
+ | |||
+ | ; Thursday 10/1 Tasks (updated 0830 10/1) | ||
+ | * Picoammeter Removal, InjSB (Francis) 5a | ||
+ | * Sample hold cables install, IN02B24 (Francis) | ||
+ | * BPM Work in IN02B2* (Francis) | ||
+ | * Chopper amplifier upgrade (Farrish) | ||
+ | * Harp upgrade to PC104 (Dela Cruz) | ||
+ | * Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a | ||
+ | * Disconnecting water and air lines from apertures and cups (Adderley) 8a | ||
+ | * Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a | ||
+ | |||
+ | ; Friday 10/2 Tasks (updated 0900 10/2) | ||
+ | * Viewer disconnects (Norris) 6a | ||
+ | * BPM Work in IN02B2* (Francis) | ||
+ | * Chopper amplifier upgrade (Farrish) | ||
+ | * Harp upgrade to PC104 (Dela Cruz) | ||
+ | * PSS Kicker Cables tie-up (SSG) | ||
+ | * Survey and Alignment control measure around gun (S&A) | ||
+ | * Load suitcase with "bad" pucks (CIS) | ||
+ | * Pump-down vacuum in front of tee for next week (CIS) | ||
− | |||
; <u>'''Tunnel Work'''</u> | ; <u>'''Tunnel Work'''</u> | ||
Line 42: | Line 76: | ||
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 | ! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 | ||
|- | |- | ||
− | | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling || I&C || I&C | + | | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher || I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps || I&C: Norris: Viewer disconnects |
|- | |- | ||
− | | 8a - 10a || CIS + SSG || RadCon: rad probes || | + | | 8a - 10a || CIS + SSG || RadCon: rad probes || SSG: Kicker magnet removal; CIS: Tiny magnet removals || CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru || S&A: Gun |
|- | |- | ||
− | | 10a - 12p || CIS + SSG || DC Power || | + | | 10a - 12p || CIS + SSG || DC Power || DC Power: Wire wrap-ups, junction box investigation || || S&A: Gun; SSG: Kicker cable tie-up |
|- | |- | ||
− | | 12p - 2p || CIS + SSG || DC Power || DC Power || DC Power || | + | | 12p - 2p || CIS + SSG || DC Power || DC Power: Wire wrap-ups, junction box investigation || DC Power || S&A: Gun |
|- | |- | ||
− | | 2p - 4p || CIS + SSG || DC Power || 3p: Moser: Safety Warden checks || || | + | | 2p - 4p || CIS + SSG || DC Power || 3p: Moser: Safety Warden checks || || S&A: Gun |
|- | |- | ||
| 4p - ?? || || || || || | | 4p - ?? || || || || || | ||
|} | |} | ||
− | * Remove suitcase | + | ; <u>'''Other Work Occurring When Convenient'''</u> |
− | * EES- | + | * Remove suitcase, Tunnel (CIS) |
− | * | + | * Harp upgrade, InjSB (I&C) |
− | * DC Power magnet | + | * ODH Head Replacement, InjSB and Tunnel (SSG) |
− | * Prebuncher | + | * PSS Chassis Removals, InjSB (SSG) |
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | ; Monday Oct 5 | ||
+ | * vacuum tests, disconnects, and pre-removal blank offs (CIS) | ||
+ | * QCM->downstream Survey and Alignment | ||
+ | * S&H cable work for iocinse4, InjSB (Francis) | ||
+ | |||
+ | ; Tuesday Oct 6 | ||
+ | * Survey and Alignment finishing up around 0L04 (S&A) | ||
+ | * U-tube operations at 0L03 (Cryo) | ||
+ | * S&H cable work for iocinse4, InjSB (Francis) | ||
+ | * Stage/prepare for craning our girders (Mech Install) | ||
+ | * Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF) | ||
+ | |||
+ | ; Wednesday Oct 7 | ||
+ | * S&H cable work for iocinse4, InjSB (Francis) | ||
+ | * Chopper SSA upgrade, InjSB (Farrish) | ||
+ | * Wein PS Work, InjSB (Windham) | ||
+ | * VIP UHV PS Work, InjSB (Windham) | ||
+ | * Harp PC104 upgrade, InjSB (Dela Cruz) | ||
+ | |||
+ | ; Thursday Oct 8 | ||
+ | * BPM work, InjSB (Francis) | ||
+ | * Chopper SSA upgrade, InjSB (Farrish) | ||
+ | * Harp PC104 upgrade, InjSB (Dela Cruz) | ||
+ | |||
+ | ; Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install | ||
+ | * Remove to test lab -- | ||
+ | ** Laser outrigger table | ||
+ | ** <strike>1st Wein girder and pedestals | ||
+ | ** 2nd Wein girder, apertures, and pedestals | ||
+ | ** Photocathode puck suitcase on cart</strike> | ||
+ | * Remove to Brett Lewis grey oil tank | ||
+ | * Penetration stone drops | ||
+ | |||
+ | Current list of Injector penetrations to be dropped: '''57, 86, 108, possibly [[Unknown Pene for Choppers | this one]]''' | ||
+ | |||
+ | Penetration drop distance [https://logbooks.jlab.org/entry/3854100 e3854100]: | ||
+ | * 34ft from floor of InjSB to floor of Inj tunnel | ||
+ | * 25ft from floor of InjSB to elevated Inj tunnel cable tray | ||
+ | |||
+ | ; Friday Oct 9 | ||
+ | * BPM Work, InjSB (Francis) | ||
+ | * Chopper SSA upgrade, InjSB (Farrish) | ||
+ | * Harp PC104 upgrade, InjSB (Dela Cruz) | ||
+ | * Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install) | ||
+ | ** Penetration above laser hut already opened | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | * Laser/Y-Chamber viewer for Y-chamber girder (Marcy) | ||
+ | * Fiducializing Y-chamber girder (S&A) | ||
+ | * Laser window under vacuum evaluations (Phil/Shukui/Caryn) | ||
+ | * Documenting early InjSB racks (Scott) | ||
+ | * Cable pulls through penetrations (EES) | ||
+ | * <strike> Fire pipe demolition? </strike> (Facilities Contractor) | ||
+ | * Wein upgrade (Carlos) -- | ||
+ | ** Finish new Wien electrodes drawing and sign-offs | ||
+ | ** Vacuum chambers to machine shop for mods | ||
+ | ** Begin creating new screens | ||
+ | * [[Tunnel Photos Oct14 2020|Injector Tunnel Photos]] from W 10/14 | ||
+ | |||
+ | |||
+ | ; Monday Oct 12 | ||
+ | Tunnel -- | ||
+ | * Hooking up VIPs to new 18V PS for load testing (Marcy/Scott) | ||
+ | * Cable pulls through penetrations (EES) | ||
+ | |||
+ | InjSB -- | ||
+ | * BPM Cable Pulls through Penetration 86 (Francis) | ||
+ | * Chopper SSA upgrade (Farrish) | ||
+ | * Harp to PC104 upgrade (Dela Cruz) | ||
+ | * Early rack documentation and space optimization (Scott) | ||
+ | * PSS Upgrade work (IN02BNI, B29, B30) (SSG) | ||
+ | |||
+ | |||
+ | ; Tuesday Oct 13 | ||
+ | Tunnel -- | ||
+ | * Cable pulls through penetrations (EES) | ||
+ | * Resistor box evaluation (Coleman) | ||
+ | |||
+ | InjSB -- | ||
+ | * BPM Work, IN02B{*} (Francis) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | * Harp to PC104 upgrade, IN03B07 (Dela Cruz) | ||
+ | * Early rack documentation and space optimization, IN01B{02-05} (Scott) | ||
+ | * PSS Upgrade, IN02{BNI, B29, B30} (SSG) | ||
+ | |||
+ | |||
+ | ; Wednesday Oct 14 | ||
+ | Tunnel -- | ||
+ | * Cable pulls through penetrations (EES) | ||
+ | * Safety warden walk-through (Moser) | ||
+ | |||
+ | InjSB -- | ||
+ | * BPM Work, IN02B{*} (Francis) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | * Harp to PC104 upgrade, IN03B07 (Dela Cruz) | ||
+ | * Early rack documentation and space optimization, IN01B{02-05} (Scott) | ||
+ | * PSS Upgrade, IN02{BNI, B29, B30} (SSG) | ||
+ | * Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser) | ||
+ | * Safety warden walk-through (Moser) | ||
+ | * Conduit in penetration 135 (Electricians) | ||
+ | |||
+ | |||
+ | ; Thursday Oct 15 | ||
+ | Tunnel -- | ||
+ | * S&A Level surveys | ||
+ | |||
+ | InjSB -- | ||
+ | * BPM Work, IN0{2,3}B{*} (Francis) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | * Harp to PC104 upgrade, IN03B07 (Dela Cruz) | ||
+ | * Early rack documentation and space optimization, IN01B{02-05} (Scott) | ||
+ | * PSS Upgrade, IN02{BNI, B29, B30} (SSG) | ||
+ | * 20A PS Install, Rack re-org, IN02B22 (DC Power) | ||
+ | |||
+ | ; Friday Oct 16 | ||
+ | Tunnel -- | ||
+ | * Cable pulls through penetrations (EES) | ||
+ | * Mott cable removals (Scott/Riad, EES) | ||
+ | |||
+ | InjSB -- | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | * Harp to PC104 upgrade, IN03B07 (Dela Cruz) | ||
+ | * Early rack documentation and space optimization, IN01B{02-05} (Scott) | ||
+ | * PSS Upgrade, IN02{BNI, B29, B30} (SSG) | ||
+ | * 20A PS Install, Rack re-org, IN02B22 (DC Power) | ||
+ | * IN02B26 Power Lock-Out, ~915a (DC Power) | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | ;Non-Tunnel Work | ||
+ | * Build new Y-chamber viewer => '''Y-built w/test screen, Laser being built.''' | ||
+ | * Use test screen + laser + S&A to verify position of first viewer => '''This week''' | ||
+ | * Install + align + vacuum seal (2) viewers => '''target this week''' | ||
+ | * Caryn will confirm but identified best ‘mushroom’ window, attach => '''done''' | ||
+ | * ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => '''???''' | ||
+ | * Carlos' Wien-mania! | ||
+ | |||
+ | ;Tunnel Work | ||
+ | * Complete remove old keV Mott cables => '''done''' | ||
+ | * Complete remove old gun HV cables => '''done''' | ||
+ | * Jim pulls Wien PS cables? => '''done''' | ||
+ | * Does Wien HV cable pull start? => '''starting this week''' | ||
+ | * Scott will finish tie back of cables on tunnel floor to cable tray => '''done''' | ||
+ | * Refill 86? => '''no, not yet''' | ||
+ | |||
+ | ; Standing Injector Service Building Work | ||
+ | * BPM Work, IN0{2,3}B{*} (Francis) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | * Harp to PC104 upgrade, IN03B07 (Dela Cruz) | ||
+ | * Early rack documentation and space optimization, IN01B{02-05} (Scott) | ||
+ | * PSS Upgrade, IN02{BNI, B29, B30} (SSG) | ||
+ | * 20A PS Install, Rack re-org, IN02B22 (DC Power) | ||
+ | |||
+ | ; Monday Oct 19 | ||
+ | Tunnel -- | ||
+ | * Cryo u-tube pulls for 0L0{2,3,4} | ||
+ | |||
+ | ; Tuesday Oct 20 | ||
+ | Tunnel -- | ||
+ | * Cable pulls and removals | ||
+ | |||
+ | InjSB -- | ||
+ | * BPM Work, IN0{2,3}B{*} (Francis) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | * Harp to PC104 upgrade, IN03B07 (Dela Cruz) | ||
+ | * Early rack documentation and space optimization, IN01B{02-05} (Scott) | ||
+ | * PSS Upgrade, IN02{BNI, B29, B30} (SSG) | ||
+ | * 20A PS Install, IN02B22, 2p - 4p (DC Power) | ||
+ | |||
+ | ; Wednesday Oct 21 | ||
+ | Tunnel -- | ||
+ | * S&A Verify line with new control | ||
+ | |||
+ | InjSB -- | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person) | ||
+ | * Viewer work, IN03B07, 6a - 9a (Norris) | ||
+ | * Wien controls work, IN01B03, 6a - 9a (Dela Cruz) | ||
+ | * M56 Hardware Removal from IN02B22, (I&C) | ||
+ | |||
+ | |||
+ | ; Thursday Oct 22 | ||
+ | InjSB -- | ||
+ | * Wien Magnet PS Install, IN02B22, afternoon (DC Power) | ||
+ | * Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham) | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person) | ||
+ | * Viewer work, IN03B07, 6a - 9a (Norris) | ||
+ | * Wien controls work, IN01B03, 6a - 9a (Dela Cruz) | ||
+ | |||
+ | |||
+ | ; Friday Oct 23 | ||
+ | Tunnel -- | ||
+ | * Vacuum work clean room craned in 6a - 8a (Mech Install) | ||
+ | * Clean room setup and prepping (Marcy) | ||
+ | * Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames) | ||
+ | * Laser room work (Shukui) | ||
+ | |||
+ | InjSB -- | ||
+ | * Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham) | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer) | ||
+ | * Viewer work, IN03B07, 6a - 9a (Norris) | ||
+ | * Wien controls work, IN01B03, 6a - 9a (Dela Cruz) | ||
+ | * 20A PS Install, IN02B22 (DC Power) | ||
+ | |||
+ | |||
+ | <u>'''Inj Service Building Work'''</u> | ||
+ | |||
+ | [[File:InjSB Racks.png|1000px]] | ||
+ | |||
+ | {| class="wikitable" | ||
+ | |- | ||
+ | ! Time !! Wed 10/21 !! Thu 10/22 !! Fri 10/23 | ||
+ | |- | ||
+ | | 5a - 9a || Dela Cruz, Norris, <strike>Francis</strike> || Dela Cruz, Norris, <strike>Francis</strike> || Dela Cruz, Norris, <strike>Francis</strike> | ||
+ | |- | ||
+ | | 9a - 12p || <strike>Francis</strike>, SSG, <strike>Windham</strike> || <strike>Francis</strike>, SSG || <strike>Francis,</strike> SSG, Windham | ||
+ | |- | ||
+ | | 12p - 4p || DC Power, SSG, <strike>Windham, Francis</strike> || DC Power, SSG, Windham, <strike>Francis</strike> || DC Power, SSG, Windham, <strike>Francis</strike> | ||
+ | |} | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | ;Tunnel work | ||
+ | * Remove NEG filter from HV chamber ✅ | ||
+ | * Setup mobile cleanroom over HV chamber ✅ | ||
+ | * Vent Gun3 chamber to test Gun3 valve ✅ | ||
+ | * Vent Gun2 chamber to test Gun2 valve ✅ | ||
+ | * Remove 2I NEG beam line, remove NEG pedestal (temporarily) ✅ | ||
+ | * Replace 10” flange + SHV connector + blank off + pump down ✅ | ||
+ | * Prep Gun3 & Y-chamber for Install to remove ✅ | ||
+ | * Wrap up UHV ion pump power supply power tests ✅ | ||
+ | * INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 ✅ | ||
+ | * S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) ✅ | ||
+ | |||
+ | ;Non-Tunnel Work | ||
+ | * Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve ''on-going'' | ||
+ | * Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] | ||
+ | ::-Wien magnetic field mapping ''next couple weeks'' | ||
+ | ::-Bubba assembles the fixtures ✅ | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building Work'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#E6E6FA" | ||
+ | ! '''Location'''<br>Time !! Mon 10/26 !! Tue 10/27 !! Wed 10/28 !! Thu 10/29 !! Fri 10/30 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' || Gun2 Table Move <br> Y-Chamber+Gun3 Removal || | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || Francis, SSG || Francis, Windham, SSG || Francis, Windham, SSG || Dela Cruz, Norris, Francis, SSG || Francis, SSG | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' || 9a CIS+MechInstall Walk-Thru || Wien Cable Pulls || Cryo 0L02 L-tube pull <br> Fire pipe walk thru <br> S&A Point Layouts | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || SSG || Windham, SSG || Windham, SSG <br> Trim Rack Checks || SSG || SSG | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' <br> 3p:Videographer Tour || || || S&A Point Layouts | ||
+ | |} | ||
+ | |||
+ | [[File:InjSB Week6.png|1000px]] | ||
+ | |||
+ | |||
+ | ; Mon Oct 26 | ||
+ | Tunnel -- | ||
+ | * Gun vacuum work, 9a - 4p (CIS) | ||
+ | |||
+ | InjSB -- | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer) | ||
+ | * Wien controls work, IN01B03, 6a - 9a (Dela Cruz) | ||
+ | * Viewer work, IN03B07, 6a - 9a (Norris) | ||
+ | * BPM Work, IN03B{05-08, 23} 5a - 1p (Francis) | ||
+ | * 20A Wien Magnet PS Install, IN02B22 (Coleman) | ||
+ | * LLRF air temperature control system removal from IN01B13? (Plawski?) | ||
+ | |||
+ | ; Tues Oct 27 | ||
+ | Tunnel -- | ||
+ | * Gun vacuum work, 9a - 3p (CIS) | ||
+ | * Videographer Tour, 3p+ (K. Carter + two videographers) | ||
+ | |||
+ | InjSB -- | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer) | ||
+ | * Wien controls work, IN01B03, 6a - 9a (Dela Cruz) | ||
+ | * Viewer work, IN03B07, 6a - 9a (Norris) | ||
+ | * BPM Work, IN03B{05-08, 23} 5a - 1p (Francis) | ||
+ | * CIS Rack Work, IN01B{00-05} 9a - 4p (Windham) | ||
+ | * 20A Wien Magnet PS Install, IN02B22 (Coleman) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | * LLRF air temperature control system removal from IN01B13? (Plawski?) | ||
+ | |||
+ | ; Wed Oct 28 | ||
+ | Tunnel -- | ||
+ | * CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a | ||
+ | |||
+ | InjSB -- | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer) | ||
+ | * Wien controls work, IN01B03, 6a - 9a (Dela Cruz) | ||
+ | * Viewer work, IN03B07, 6a - 9a (Norris) | ||
+ | * BPM Work, IN03B{05-08, 23} 5a - 1p (Francis) | ||
+ | * CIS Rack Work, IN01B{00-05} 9a - 4p (Windham) | ||
+ | * Trim Card Checks, IN02B{10+11+26} + IN04B10, 12p-1p (Richardson) | ||
+ | Other Possible Work.... | ||
+ | * 20A Wien Magnet PS Install, IN02B22 (Coleman) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11}, (Farrish) | ||
+ | |||
+ | |||
+ | ; Thur Oct 29 | ||
+ | Tunnel -- | ||
+ | * Gun2 move, 5a - 8a (Mech Install) | ||
+ | * Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install) | ||
+ | * Wien HV and control cable pulls, 9a - 1p (Dela Cruz) | ||
+ | |||
+ | InjSB -- | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer) | ||
+ | * Wien controls work, IN01B03, 6a - 1p (Dela Cruz) | ||
+ | * Viewer work, IN03B07, 6a - 1p (Norris) | ||
+ | * BPM Work, IN03B{05-08, 23} 5a - 1p (Francis) | ||
+ | Other possible work.... | ||
+ | * 20A Wien Magnet PS Install, IN02B22 (Coleman) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11}, (Farrish) | ||
+ | |||
+ | ; '''All Hallows' Eve ''Eve'' 👻''' (Fri 10/30) | ||
+ | Tunnel -- | ||
+ | * Cryo L-tube Removal from 0L02, 8a - 12p (Cryo) | ||
+ | * Fire pipe demo job walk-through, 12p (Grames, Suhring, Renzo) | ||
+ | * Point Layouts, after cryo (S&A) | ||
+ | |||
+ | InjSB -- | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer) | ||
+ | * Wien controls work, IN01B03, 6a - 1p (Dela Cruz) | ||
+ | * Viewer work, IN03B07, 6a - 1p (Norris) | ||
+ | * BPM Work, IN03B{05-08, 23} 5a - 1p (Francis) | ||
+ | Other possible work.... | ||
+ | * 20A Wien Magnet PS Install, IN02B22 (Coleman) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11}, (Farrish) | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 7 (Nov 2 - Nov 6) == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | '''Fire pipe removal, viewer design, modify existing pedestals, Wien filter mapping''' | ||
+ | |||
+ | ;'''Tunnel work''' | ||
+ | ;Mon/Tue | ||
+ | #INSTALL crane support (move Y-girder, Gun3 chamber, anything else back to TL1137) | ||
+ | #CIS take opportunity to a) cover your stuff before fire pipe demo, b) clean up cabinets, toolbox | ||
+ | #EES-IC Cable Pulls, Termination, and Routing | ||
+ | ;Wed/Thu and maybe Fri | ||
+ | #Fire pipe demolition | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | * Complete Y-chamber: add viewers, add laser vacuum window, add NEG towers, add gun valve | ||
+ | * Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] => H/V-wien magnetic field mapping | ||
+ | |||
+ | ;'''InjSB Work''' | ||
+ | * Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) -- | ||
+ | ** Comm chassis to digiport server | ||
+ | * PSS Upgrade, IN02B{NI, 29, 30} (Beizer) | ||
+ | * Viewer work, IN03B0{6+7} (Norris) | ||
+ | * BPM Work, IN03B{05-08, 23} (Francis) | ||
+ | * CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | Other possible work... | ||
+ | * 20A Wien Magnet PS Install (Coleman) | ||
+ | * Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 11/2 !! Tue 11/3 <br> Election Day 🇺🇸 !! Wed 11/4 !! Thu 11/5 !! Fri 11/6 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work || BPM, Viewer, Wien Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || Wien + viewer cable pulls <br> INSTALL Crane Outs || Wien + viewer cable pulls || Fire pipe demo|| Fire pipe demo || F(riday) | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work || PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || Wien + viewer cable pulls || Wien + viewer cable pulls || Fire pipe demo || Fire pipe demo || F(loat) | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || M || T || Fire pipe demo || Fire pipe demo || F | ||
+ | |} | ||
+ | |||
+ | [[File:InjSB Week7.png|1000px]] | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | ;'''Tunnel work''' | ||
+ | # Tue - S&A is queued up to set new(er) gun foot pad points | ||
+ | # Tue/Wed - Shaun predicts 4 pedestals arrive, Jenord inspects them; other peds exist in tunnel - thank you Phil/Shaun! | ||
+ | # Wed/Thu/Fri - Install drills and drops anchors, prepare grout form?, maybe we return gun table (Tom, best guess for the fire pipe install?) | ||
+ | |||
+ | ;'''ME work''' | ||
+ | * S&A drop revised points for table base pads. ECD 11/10. '''done''' | ||
+ | |||
+ | * 2I solenoid – '''done''' | ||
+ | ::SG print full size drill template for Neil. | ||
+ | ::Check fit of template. | ||
+ | |||
+ | * Neil – Drill holes into top of solenoid stand (existing item and is currently in place) using drill template provided by Shaun. '''done''' | ||
+ | |||
+ | * Neil drill anchor holes in floor '''done''' | ||
+ | ::HVC table base pads. '''done''' | ||
+ | ::Wien Girder Pedestals. '''done''' | ||
+ | ::Aperture Girder Pedestals. '''done''' | ||
+ | ::Details have been provided to Neil. '''done''' | ||
+ | |||
+ | * Y chamber girder | ||
+ | ::Design new v-block mounting for Y & ion pump due to angle change of Y. | ||
+ | ::Fabricate or modifications. | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | # Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] - Wien magnet mapping, HVPS system controls (ADC/DAC), Switchbox build | ||
+ | # Complete Y-chamber build : laser window + (2) viewers + NEG Tower + Valve (gun3!?) | ||
+ | # A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing | ||
+ | # Prebuncher vacuum repair, leak check | ||
+ | ::*Did the leak check braze joint happen? | ||
+ | ::*Did a final probe port length get decided? | ||
+ | ::*Can we resolve these question, repair the probe port, clean, ready for testing by Friday? | ||
+ | # Submit PR for PSS kicker | ||
+ | |||
+ | ;'''ISB Work''' | ||
+ | # Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) -- | ||
+ | #* Wire HV PS | ||
+ | #* Install Comm chassis | ||
+ | # PSS Upgrade, IN02B{NI, 29, 30} (Beizer) | ||
+ | # Viewer upgrades, IN03B07 (Norris) | ||
+ | # Harp upgrades, IN03B07 (Dela Cruz) | ||
+ | # BPM Work, IN03B{05-08, 23} (Francis) Phase I: ✅; jump-start on Phase II ✅ | ||
+ | # CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | # Chopper SSA upgrade, back of IN01B{03-11} (Farrish) | ||
+ | # First Aid Cabinet re-stocks, back wall behind IN02B22ish + bottom of access stairs, (Occ Med + vendor), date TBD | ||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 11/9 !! Tue 11/10 !! Wed 11/11 !! Thu 11/12 !! Fri 11/13 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || BPM, Viewer, Wien Work || BPM, Viewer, Wien, Harp Work || BPM, Viewer, Wien, Harp Work || BPM, Viewer, Wien, Harp Work || Viewer, Wien, Harp Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || Viewer Cable Pulls || T || INSTALL Pedestals, base pads, solenoid stand drilling || INSTALL work <br> Viewer Cable Pulls || S&A Survey Pedestals | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || PSS Upgrade <br> BPM, Viewer, Wien Work <br> CIS Rack Work || PSS Upgrade <br> BPM, Harp, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Harp, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> BPM, Harp, Viewer, Wien Work <br> CIS Rack Work|| PSS Upgrade <br> Harp, Viewer, Wien Work <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || Viewer cable pulls || S&A Sets New(er) Points <br> DC Power Resistor Box Button-Up|| INSTALL Pedestals, base pads, solenoid stand drilling || Viewer Cable Pulls <br> 11a: Laser Safety System Audit || S&A Survey Pedestals | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || M || S&A Sets New(er) Points || Cable pulls? || R || S&A Survey Pedestals | ||
+ | |} | ||
+ | |||
+ | [[File:InjSB Week8.png|1000px]] | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 9 (Nov 16 - Nov 20) == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | # Continue preparing new Y-chamber | ||
+ | # A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing | ||
+ | # Prebuncher -- RF testing/tuning | ||
+ | # Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] => | ||
+ | #* Review V-wien magnetic field mapping results and determine any remaining desired measurements | ||
+ | #* Finish V-wien field mapping and move to horizontal | ||
+ | #* Wien quad hardware arrivals? | ||
+ | #* Install HV switcher chassis | ||
+ | # 200kV PSS kicker fabrication | ||
+ | |||
+ | ;'''Tunnel work ''' | ||
+ | # INSTALL grouts in pedestals (Mon/Tue) ''done?'' | ||
+ | # Fire pipe demo (Wed/Thur/Fri) | ||
+ | |||
+ | ;'''ISB Work''' | ||
+ | # Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) | ||
+ | # PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer) | ||
+ | # Viewer upgrades, IN03B07 (Norris) | ||
+ | # Harp upgrades, IN03B07 (Dela Cruz) | ||
+ | # CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 11/16 !! Tue 11/17 !! Wed 11/18 !! Thu 11/19 !! Fri 11/20 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || INSTALL Grout pedestals || T || Fire pipe demo || Fire pipe demo || Lifting Plate Load Test | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || Viewer, Harp, Wien Work <br> CIS Rack Work || Viewer, Harp, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || INSTALL Grout pedestals || Laser room/table work <br> Ceiling Lifting Plate Install || Fire pipe demo || Fire pipe demo || F | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || M || Laser room/table work || Fire pipe demo || Fire pipe demo || F | ||
+ | |} | ||
+ | |||
+ | [[File:InjSB Week9.png|1000px]] | ||
+ | |||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 10 (Nov 23 - Nov 25 🦃) == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | # Complete assembly of new Y-chamber | ||
+ | # Magnetic mapping of spare aperture cube | ||
+ | # A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing | ||
+ | # Prebuncher -- RF testing/tuning | ||
+ | # Wien-mania! [[200kV Wien filter - FINAL | (high level schedule)]] => | ||
+ | #* Horizontal Wien magnetic assembly and field mapping | ||
+ | #* Bake V-wien electrode assembly with vacuum chamber | ||
+ | #* V-wien HV test at UITF | ||
+ | #* Resistor box testing at UITF? | ||
+ | |||
+ | ;'''Tunnel work ''' | ||
+ | # Opportunistic cable pulls -- who wants to do some? Good week for it. | ||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | # Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) | ||
+ | # PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer) | ||
+ | # Viewer upgrades, IN03B07 (Norris) | ||
+ | # Harp upgrades, IN03B07 (Dela Cruz) | ||
+ | # CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 11/23 !! Tue 11/24 !! Wed 11/25 !! Thu 🦃 11/26 !! Fri 11/27 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || Viewer, Harp, Wien Work || || | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || M || T || W || || | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || Viewer, Harp, Wien Work <br> CIS Rack Work || Viewer, Harp, Wien Work <br> CIS Rack Work|| Harp, Viewer, Wien Work <br> CIS Rack Work|| || | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || M || T || W || || | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || || | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || M || T || W || || | ||
+ | |} | ||
+ | |||
+ | [[File:InjSB Week9.png|1000px]] | ||
+ | |||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 11 (Nov 30 - Dec 4) == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | * H-Wien | ||
+ | **plate ready at shop, mic and test fit @ MMF | ||
+ | **order (4) Ni plates | ||
+ | * V-Wien | ||
+ | ** Start HV tests @ UITF | ||
+ | * MHD | ||
+ | ** complete thermal test >2.5A | ||
+ | ** measure field profile and BL/I for CED | ||
+ | * DR | ||
+ | ** measure DR per Jay's plan | ||
+ | * A1/A2 cubes | ||
+ | ** complete assembly (coils + aperture), test motion and shorts | ||
+ | **S&A fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) | ||
+ | * PSS kicker | ||
+ | ** vendor quotes? | ||
+ | ** place order | ||
+ | |||
+ | ;'''Tunnel work''' | ||
+ | * Install | ||
+ | ** Y girder + 2I solenoid from 1137 to tunnel | ||
+ | ** Gun table to foot pads | ||
+ | |||
+ | * S&A | ||
+ | ** Pre-align Y girder | ||
+ | ** Pre-align gun | ||
+ | |||
+ | * PSS/CIS | ||
+ | ** Complete laser bypass | ||
+ | ** Align laser - test at window, viewer hole, cathode/flange | ||
+ | |||
+ | * CIS/S&A | ||
+ | ** 2I solenoid on pedestal | ||
+ | ** 2I vacuum connection (valve to gun) | ||
+ | ** Final align | ||
+ | ** Final laser check | ||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | * Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) | ||
+ | * PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer) | ||
+ | * Viewer upgrades, IN03B{06-07} (Norris) | ||
+ | * Harp upgrades, IN03B07 (Dela Cruz) | ||
+ | * CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 11/30 !! Tue 12/1 !! Wed 12/2 !! Thu 12/3 !! Fri 12/4 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || M || T || W || R || F | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || M || INSTALL: Y-chamber, solenoid || PSS Laser Bypass Work || S&A: Pre-align Gun-Y || S&A: Pre-align Gun-Y | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work || CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || M || INSTALL: Y-chamber, solenoid || CIS Laser Hut Work || S&A: Pre-align Gun-Y || S&A: Pre-align Gun-Y <br> CIS Laser Alignment Work | ||
+ | |- | ||
+ | | '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || M || T || W || S&A: Pre-align Gun-Y || S&A: Pre-align Gun-Y <br> CIS Laser Alignment Work | ||
+ | |} | ||
+ | |||
+ | [[File:InjSB Week11.png|1000px]] | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 12 (Dec 7 - Dec 11) == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | * Wien (Test Lab) | ||
+ | ** Test voltage divider box, calibrating UITF Matsusada HV PSs '''done, ''' ''opted to use FLUKE 1000:1 V-probe and RMS true-value multimeter'' | ||
+ | ** U-Wien electrode alignment -- install teflon spacer (CIS) '''first-pass done, ''' ''after discussions, may refine'' | ||
+ | ** Improve V-wien electrode alignment? (S&A) ''deferred'' | ||
+ | ** Receive Nickel endplates ''received, returned after finish found scratched, received again?'' | ||
+ | |||
+ | * A1/A2 cubes (Test Lab) | ||
+ | ** Assemble fixture mounting plates '''done''' | ||
+ | ** Test motion and shorts ' | ||
+ | ** Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) ''awaiting cubes'' | ||
+ | |||
+ | * Prebuncher - high power testing | ||
+ | |||
+ | * PSS kicker | ||
+ | ** build bids received, choosing one '''done''' | ||
+ | ** 12/9: req submitted | ||
+ | |||
+ | *MagTest | ||
+ | ** Wrapping up A2 measurements | ||
+ | ** Wrapping up A1 measurements | ||
+ | |||
+ | |||
+ | ;'''Tunnel work''' | ||
+ | * Wien cable pulls (Dela Cruz) | ||
+ | * Laser alignment work (CIS) '''complete for this week''' | ||
+ | * Gun -> Y-chamber vacuum connections (CIS) ''Thursday/Friday'' | ||
+ | * Viewer cable terminations (Norris) | ||
+ | |||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | * Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) | ||
+ | * PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer) | ||
+ | * Viewer upgrades, IN03B{06-07} (Norris) | ||
+ | * Harp upgrades, IN03B07 (Dela Cruz) | ||
+ | * CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 12/7 !! Tue 12/8 !! Wed 12/9 !! Thu 12/10 !! Fri 12/11 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || M || Viewer/Wien/Harp Work || Viewer/Wien/Harp Work || R || Viewer Terminations | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || CIS Laser Work || CIS Laser Work || CIS Laser Work || S&A+CIS Drive Laser Alignment || Locking in NEG-tube <br> BPM locations (CIS+S&A) | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || CIS Rack Work || CIS Rack Work <br> Viewer/Wien/Harp Work || CIS Rack Work <br> Viewer/Wien/Harp Work || CIS Rack Work || CIS Rack Work <br> Viewer Terminations <br> Wien Cabling Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || CIS Laser Work || CIS Laser Work-<br>temp Vacuum Window Install <br> Facilities HVAC Investigation || CIS Laser Work || S&A+CIS Drive Laser Alignment || CIS Pump Down Gun <br> S&A Gun/Y-Chamber | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work <br> Viewer Terminations <br> Wien Cabling Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || CIS Laser Work || CIS Laser Work <br> Facilities HVAC Investigation || CIS Laser Work || S&A+CIS Drive Laser Alignment || CIS Pump Down Gun <br> S&A Gun/Y-Chamber | ||
+ | |} | ||
+ | |||
+ | |||
+ | [[File:InjSB Week11.png|1000px]] | ||
+ | |||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 13 (Dec 14 - Dec 18) == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | * Wien (Test Lab) | ||
+ | ** U-Wien electrode parallelism evaluation after assembly w/teflon spacer block, spacer for hangers added (S&A) '''done''' | ||
+ | ** Controls work continues ''yep'' | ||
+ | ** HV PS calibration measurements, second-pass ''Friday'' | ||
+ | ** Receive Nickel endplates? '''done''' | ||
+ | |||
+ | * A1/A2 cubes (Test Lab) | ||
+ | ** Assembling A1/A2 cubes '''done''' | ||
+ | ** Test motion and shorts '''done''' | ||
+ | ** Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) '''A2 done, A1 completed today''' | ||
+ | |||
+ | *MagTest | ||
+ | ** Measure DR per Jay's plan ''continues'' | ||
+ | ** QW (Wien quad) lead reinforcement and field mapping ''4 done, 12 to go'' | ||
+ | |||
+ | |||
+ | ;'''Tunnel work''' | ||
+ | * Wien cable pulls (Dela Cruz) (latter half of the week) ''done?'' | ||
+ | * Viewer cable terminations? (Norris) ''near complete'' | ||
+ | * Gun -> Y-chamber vacuum pumpdown and leak check (Stutzman, Adderley) '''done''' | ||
+ | * CIS Check drive laser -> cathode -> retroreflection alignment w/assembly under vacuum '''done''' | ||
+ | * SSG Backs out of Laser Bypass workaround in support of PSS upgrades ''Friday'' | ||
+ | |||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | * Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz) | ||
+ | * PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer) | ||
+ | * Viewer upgrades, IN03B{06-07} (Norris) | ||
+ | * Harp upgrades, IN03B07 (Dela Cruz) | ||
+ | * CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 12/14 !! Tue 12/15 !! Wed 12/16 !! Thu 12/17 !! Fri 12/18 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || Viewer Terminations || Viewer Terminations || W || R || F | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || CIS Vacuum Work: <br> heating NEG chambers || CIS Vacuum Work:<br>Leak Checks || Wien HV Cable Pulls? || Wien HV Cable Pulls? || F | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || CIS Rack Work <br> Viewer Terminations || CIS Rack Work <br> Viewer Terminations || CIS Rack Work || CIS Rack Work <br> PSS Upgrades:<br>Access Room and in Racks || CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || CIS Vacuum Work: <br> heating NEG chambers || CIS Vacuum Work:<br> Leak Checks<br>CIS Laser/retroreflection checks || CIS Laser Hut Work <br> Viewer Terminations <br> Wien HV Cable Pulls? || CIS Laser Hut Work <br> Viewer Terminations || SSG Laser Bypass Backout | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work || PSS Upgrades:<br>Access Room and in Racks <br> CIS Rack Work || PSS Upgrade <br> CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || CIS Vacuum Work || CIS Vacuum Work<br>CIS Laser/retroreflection checks || CIS Laser Hut Work <br> Viewer Terminations || CIS Laser Hut Work <br> Viewer Terminations || F | ||
+ | |} | ||
+ | |||
+ | |||
+ | [[File:InjSB Week11.png|1000px]] | ||
+ | |||
+ | </div> | ||
+ | |||
+ | == Week 13.6 (Dec 21 - Dec 23) == | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | <div style="text-align: center"> | ||
+ | '''830 toolbox meetings suspended.<br>Have a safe and restful winter break.''' | ||
+ | </div> | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | |||
+ | MagTest -- | ||
+ | * DR field mapping continues | ||
+ | |||
+ | |||
+ | ;'''Tunnel work ''' | ||
+ | * Neutron detector field cable runs, above 0L03 (Gonzales) | ||
+ | * PSS upgrades -- equipment near Inj-NL gate (SSG) | ||
+ | |||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | * CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | * Viewer terminations, IN03B{06, 07} (Norris) | ||
+ | * PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere (SSG) | ||
+ | * Neutron detector system work, IN03+4 (Gonzales, Mock) | ||
+ | |||
+ | |||
+ | [[File:InjSB Week13.5.png|1000px]] | ||
+ | |||
+ | |||
+ | </div> | ||
+ | |||
+ | </div> | ||
+ | |||
+ | = Week 14 (Jan 4 - Jan 8) = | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | '''Happy New Year!!! 🎉🎉🎉''' | ||
+ | |||
+ | ;* AIPINJ Phase I Jobs for 2021 | ||
+ | * Punchlist from 12/17/20 ME meeting [[media:AIPINJ_2021_Jobs_v3.pdf]] | ||
+ | |||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | * Wien | ||
+ | ** V-Wien (Hernandez-Garcia) | ||
+ | *** remove from UITF test stand | ||
+ | *** re-assemble in ''V''ertical orientation w/new spacers, Ni endplates, and magnet | ||
+ | *** ~Wed deliver to S&A | ||
+ | *** Survey of V-wien, evaluation of electrode parallelism | ||
+ | ** Picking up new Ni endplates from machine shop, cleaning and annealing before delivery to MagTest to be used in assembly of H-wien and evaluation during field mapping (Grames) | ||
+ | ** Fabrication of HV switcher chassis continues (Dela Cruz) | ||
+ | ** Controls work continues (Croke) | ||
+ | * A1/A2 Apertures | ||
+ | ** Motor controls work continues (Windham) | ||
+ | ** A1/A2 girder build in TL continues (Adderley) | ||
+ | * MagTest | ||
+ | ** DR field mapping | ||
+ | ** Complete QW coils lead reinforcement and mapping | ||
+ | ** Begin H-wien field mapping? | ||
+ | |||
+ | |||
+ | ;'''Tunnel work ''' | ||
+ | * Prepping for Gun2 bake (Stutzman) | ||
+ | * Wien HV cable pulls? (Dela Cruz, Norris) | ||
+ | * Laser hut opto-mechanical work (Zhang) | ||
+ | * LCW walkthrough (CIS+I&C+MechInstall) | ||
+ | |||
+ | |||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | * Wien HV cable pulls?, IN01B{00+01} (Dela Cruz, Norris) | ||
+ | * PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer) | ||
+ | * CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | * Viewer upgrades, IN03B{06+07} (Norris) | ||
+ | * 15deg dipole interlock panel install, IN01B11 (Windham) | ||
+ | * iocin3 crate upgrade to VME, IN01B{04+14} (Dela Cruz) | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 1/4 !! Tue 1/5 !! Wed 1/6 !! Thu 1/7 !! Fri 1/8 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || M || T || W || R || F | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || M || Wien HV cable pulls? || MechInstall Crane Work <br> Wien HV cable pulls? <br> Viewer Terminations || Wien HV cable pulls? <br> Viewer Terminations || Wien HV cable pulls? <br> Viewer Terminations | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || CIS Rack Work || CIS Rack Work --<br>15deg Interlocks Panel || CIS Rack Work <br> iocin3 crate upgrade prep || 15deg Interlocks Panel || CIS Rack Work | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || Gun2 Bake Preps || 9a LCW Manifold WalkThru <br> Gun2 Bake Preps <br> Viewer Terminations || Gun2 Bake Preps <br> Viewer Terminations || Gun2 Bake Preps <br> Viewer Terminations || Gun2 Bake Preps <br> Viewer Terminations | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || CIS Rack Work <br>PSS Upgrades || CIS Rack Work --<br>15deg Interlocks Panel <br>PSS Upgrades || CIS Rack Work <br> iocin3 crate upgrade prep <br> PSS Upgrades || 15deg Interlocks Panel <br>PSS Upgrades || CIS Rack Work <br>PSS Upgrades | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || Gun2 Bake Preps || Gun2 Bake Preps || Gun2 Bake Preps || Gun2 Bake Preps || Gun2 Bake Preps | ||
+ | |} | ||
+ | |||
+ | |||
+ | [[File:InjSB Week14.png|999px]] | ||
+ | |||
+ | </div> | ||
+ | |||
+ | = Week 15 (Jan 11 - Jan 15) = | ||
+ | <div class="mw-collapsible"> | ||
+ | |||
+ | ;'''Non-Tunnel Work''' | ||
+ | * Wien (Hernandez-Garcia) | ||
+ | ** Bake V-wien | ||
+ | ** V-wien HV soak | ||
+ | ** Fabrication of HV switcher chassis (Dela Cruz) | ||
+ | * A1/A2 girder build (Adderley) | ||
+ | * Rectify viewer air cylinder lengths? (Stutzman) | ||
+ | |||
+ | * MagTest | ||
+ | ** DR field mapping | ||
+ | ** Complete QW coils lead reinforcement and mapping | ||
+ | ** Begin H-wien field mapping? | ||
+ | |||
+ | |||
+ | ;'''Tunnel work ''' | ||
+ | * Photocathode suitcase bake (Stutzman, Adderley) | ||
+ | * Wien HV cable pulls? (Dela Cruz, Norris) | ||
+ | * Laser hut work (Zhang) | ||
+ | * iocin3 job Tuesday | ||
+ | ::Gun HV control => no problem | ||
+ | ::Some vacuum => no problem | ||
+ | ::Some FSD => no problem | ||
+ | ::Insertables (viewers etc.) => no problem | ||
+ | ::Some Pockels cell & RTP cell controls => i turned off RTP HV PS already | ||
+ | ::Chopping aperture (not sure how current this is) => no problem | ||
+ | ::Scraper (think this is redundant?) => do we remove now??? | ||
+ | ::Maybe some old laser controls (ocelot?) => is this really a running app??? | ||
+ | ::An application called pol_source, which has controls for a number of boards - IP Digital 24, BASIC stepper motor, IpOpto. => => what is this connected to??? | ||
+ | ::Are the remaining 4-laser apps on iocin3b? Will that mini-crate be replaced or merged? Any other apps on iocin3? | ||
+ | |||
+ | |||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | * ⚡⚡⚡'''Power Outage'''⚡⚡⚡ I-BT Breaker Panel Work -- adding 50A circuit for new chopper SSA along with 225A main breaker <br> Details of what will lose power in [http://devweb.acc.jlab.org/CSUEApps/atlis/task/21696 ATLis 21696], Tunnel and SB racks affected | ||
+ | * PSS Upgrades -- energizing new equipment, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer) | ||
+ | * CIS Rack Work, IN01B{00-05} (Windham) | ||
+ | * Viewer upgrades, IN03B{06+07} (Norris) | ||
+ | * 15deg dipole interlock panel install, IN01B11 (Windham) | ||
+ | * iocin3 crate upgrade to VME, IN01B{04 + 14} (Dela Cruz) | ||
+ | ** iocin3 will be down Monday 1/11 morning | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 1/11 !! Tue 1/12 !! Wed 1/13 !! Thu 1/14 !! Fri 1/15 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>'''All Day''' || Safing out equipment for iocin3 work || T || W || Breaker Panel Work || Float for breaker panel work | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br> Morning || M || iocin3 VME upgrade <br> 15deg interlock work || W || Breaker Panel Work || F | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br> Afternoon || PSS Upgrades || 15deg interlock work <br> PSS Upgrades || PSS Upgrades || Breaker Panel Work <br> PSS Upgrades || PSS Upgrades | ||
+ | |- | ||
+ | | '''Tunnel'''<br> All Day|| Suitcase bake <br> Safing out equipment for iocin3 work || Suitcase bake || W || Breaker Panel Work || Float for breaker panel work | ||
+ | |- | ||
+ | | '''Tunnel'''<br> Morning || M || T || W || Breaker Panel Work || F | ||
+ | |- | ||
+ | | '''Tunnel'''<br> Afternoon || M || T || W || Breaker Panel Work || F | ||
+ | |} | ||
+ | |||
+ | [[File:InjSB Week14.png|1000px]] | ||
+ | |||
+ | |||
+ | </div> | ||
+ | |||
+ | = Week 16 (Jan 18 - Jan 22) Fire pipe install? = | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | |||
+ | ;'''Non-Tunnel Work--''' | ||
+ | |||
+ | ;'''Tunnel work ''' | ||
+ | |||
+ | ;'''ISB Work ''' | ||
+ | |||
+ | |||
+ | <u>'''Injector Tunnel and Service Building'''</u> | ||
+ | {| class="wikitable" style="text-align: center" | ||
+ | |- style="background-color:#C3C8D4" | ||
+ | ! '''Location'''<br>Time !! Mon 1/18 !! Tue 1/19 !! Wed 1/20 !! Thu 1/21 !! Fri 1/22 | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>5a - 9a || M || T || W || R || F | ||
+ | |- | ||
+ | | '''Tunnel'''<br>5a - 9a || M || T || W || R || F | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>9a - 12p || M || T || W || R || F | ||
+ | |- | ||
+ | | '''Tunnel'''<br>9a - 12p || M || T || W || R || F | ||
+ | |- style="background-color:#F0F8FF" | ||
+ | | '''InjSB'''<br>12p - 4p || M || T || W || R || F | ||
+ | |- | ||
+ | | '''Tunnel'''<br>12p - 4p || M || T || W || R || F | ||
+ | |} | ||
+ | |||
+ | </div> | ||
+ | |||
+ | = Penetration Work = | ||
+ | <div class="mw-collapsible mw-collapsed"> | ||
+ | '''InjSB Penetrations that are open''' (click for pictures): | ||
+ | '''[[PenetrationALH|above laser hut]], [[Penetration58|58]], [[Penetration86|86]], [[Penetration108|108]], [[Penetration135|135]]''' | ||
+ | * 34ft from floor of InjSB to floor of Inj tunnel | ||
+ | * 25ft from floor of InjSB to elevated Inj tunnel cable tray | ||
+ | |||
+ | '''Penetration Cable Pulls/Removals --''' | ||
+ | * Tony pulling new Wien E-field HV cables | ||
+ | * Norris removing old Cat5 viewer cables | ||
+ | * Norris pulling new viewer cables | ||
+ | * <strike> Riad/Scott removing old Mott HV cables </strike> | ||
+ | * <strike> Coleman pulling new Wien B-field magnet cables </strike> | ||
+ | * Cole pulling new neutron detector cables (above 0L03) | ||
+ | * <strike> Scott pulling motor control cables for A1++ </strike> | ||
− | + | [[File:InjSB Racks.png | 1000px]] | |
− | + | </div> | |
− | === | + | = Fire System Work = |
+ | <div class="mw-collapsible"> | ||
+ | Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices. | ||
− | + | '''update 11/9:''' 25% of demo completed | |
− | + | <br> | |
− | + | '''update 11/23:''' demo completed | |
+ | <br> | ||
+ | '''update 12/8:''' fire pipe installation in Injector <s>slated for Winter break ~12/21 - 1/3</s> <br> "The drawings needed prior to fabrication of the INJ fire pipe have not gone through the system." No fire pipe install work over winter break. | ||
+ | <br> | ||
+ | '''update 1/7/21: Tentative fire pipe install to occur week of 1/18 in tunnel. Should take 3-4 days, so with the holiday on Monday, likely the rest of the week.''' <br>Further fire pipe work upstairs in the service will also need 3-4 days, but won't be constant (i.e. contractor will be in and out). | ||
− | + | </div> | |
− | + |
Latest revision as of 08:24, 11 January 2021
Contents
- 1 2020 Weeks 1 through 13
- 1.1 Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups
- 1.2 Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- 1.3 Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- 1.4 Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- 1.5 Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- 1.6 Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- 1.7 Week 7 (Nov 2 - Nov 6)
- 1.8 Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- 1.9 Week 9 (Nov 16 - Nov 20)
- 1.10 Week 10 (Nov 23 - Nov 25 🦃)
- 1.11 Week 11 (Nov 30 - Dec 4)
- 1.12 Week 12 (Dec 7 - Dec 11)
- 1.13 Week 13 (Dec 14 - Dec 18)
- 1.14 Week 13.6 (Dec 21 - Dec 23)
- 2 Week 14 (Jan 4 - Jan 8)
- 3 Week 15 (Jan 11 - Jan 15)
- 4 Week 16 (Jan 18 - Jan 22) Fire pipe install?
- 5 Penetration Work
- 6 Fire System Work
2020 Weeks 1 through 13
Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Monday 9/28 Tasks (updated 0915 9/28)
- Power down Wein system (Scott/Joe)
- Power down and remove DecaRad system (Scott)
- Return gun valve config to "normal" (Marcy)
- Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
- PSS Kickers and associated chassis removal (SSG)
- Laser table disassembly (Shukui/Scott)
- Tuesday 9/29 Tasks (updated 0930 9/29)
- (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
- (Done) Disconnect aperture and cup signal cables (Pete) 5a
- Disconnect rad probes (Melvin) 8a
- Tunnel magnet disconnects (Diggs, Delk) 10a
- (Done) Removal of old chopper amps from rack (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- ODH Head Replacements (SSG)
- Document existing Wein cabling and power off PS (Scott)
- Wednesday 9/30 Tasks (updated 0900 9/30)
- RF Prebuncher disconnects (Farrish) 6a
- Vacuum Component Labeling (Greenfield, Gonzales) 430a
- Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
- Tiny magnet removals (Scott, Grames) 9a
- PSS Kicker Magnet removal (SSG) 9a
- Sample hold cables install, InjSB (Francis)
- Remaining PSS Interface chassis removal (SSG)
- Harp upgrade to PC104 (Dela Cruz)
- Moser transfers CCOC phone @1430, to reach moving forward x5089
- Thursday 10/1 Tasks (updated 0830 10/1)
- Picoammeter Removal, InjSB (Francis) 5a
- Sample hold cables install, IN02B24 (Francis)
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
- Disconnecting water and air lines from apertures and cups (Adderley) 8a
- Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
- Friday 10/2 Tasks (updated 0900 10/2)
- Viewer disconnects (Norris) 6a
- BPM Work in IN02B2* (Francis)
- Chopper amplifier upgrade (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- PSS Kicker Cables tie-up (SSG)
- Survey and Alignment control measure around gun (S&A)
- Load suitcase with "bad" pucks (CIS)
- Pump-down vacuum in front of tee for next week (CIS)
- Tunnel Work
Time | Mon 9/28 | Tue 9/29 | Wed 9/30 | Thu 10/1 | F 10/2 |
---|---|---|---|---|---|
4a - 8a | I&C; 5a: Francis: BPMs, Cups, Apertures | I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher | I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps | I&C: Norris: Viewer disconnects | |
8a - 10a | CIS + SSG | RadCon: rad probes | SSG: Kicker magnet removal; CIS: Tiny magnet removals | CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru | S&A: Gun |
10a - 12p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | S&A: Gun; SSG: Kicker cable tie-up | |
12p - 2p | CIS + SSG | DC Power | DC Power: Wire wrap-ups, junction box investigation | DC Power | S&A: Gun |
2p - 4p | CIS + SSG | DC Power | 3p: Moser: Safety Warden checks | S&A: Gun | |
4p - ?? |
- Other Work Occurring When Convenient
- Remove suitcase, Tunnel (CIS)
- Harp upgrade, InjSB (I&C)
- ODH Head Replacement, InjSB and Tunnel (SSG)
- PSS Chassis Removals, InjSB (SSG)
Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network
- Monday Oct 5
- vacuum tests, disconnects, and pre-removal blank offs (CIS)
- QCM->downstream Survey and Alignment
- S&H cable work for iocinse4, InjSB (Francis)
- Tuesday Oct 6
- Survey and Alignment finishing up around 0L04 (S&A)
- U-tube operations at 0L03 (Cryo)
- S&H cable work for iocinse4, InjSB (Francis)
- Stage/prepare for craning our girders (Mech Install)
- Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
- Wednesday Oct 7
- S&H cable work for iocinse4, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Wein PS Work, InjSB (Windham)
- VIP UHV PS Work, InjSB (Windham)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Thursday Oct 8
- BPM work, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
- Remove to test lab --
- Laser outrigger table
-
1st Wein girder and pedestals - 2nd Wein girder, apertures, and pedestals
- Photocathode puck suitcase on cart
- Remove to Brett Lewis grey oil tank
- Penetration stone drops
Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one
Penetration drop distance e3854100:
- 34ft from floor of InjSB to floor of Inj tunnel
- 25ft from floor of InjSB to elevated Inj tunnel cable tray
- Friday Oct 9
- BPM Work, InjSB (Francis)
- Chopper SSA upgrade, InjSB (Farrish)
- Harp PC104 upgrade, InjSB (Dela Cruz)
- Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
- Penetration above laser hut already opened
Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild
- Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
- Fiducializing Y-chamber girder (S&A)
- Laser window under vacuum evaluations (Phil/Shukui/Caryn)
- Documenting early InjSB racks (Scott)
- Cable pulls through penetrations (EES)
-
Fire pipe demolition?(Facilities Contractor) - Wein upgrade (Carlos) --
- Finish new Wien electrodes drawing and sign-offs
- Vacuum chambers to machine shop for mods
- Begin creating new screens
- Injector Tunnel Photos from W 10/14
- Monday Oct 12
Tunnel --
- Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
- Cable pulls through penetrations (EES)
InjSB --
- BPM Cable Pulls through Penetration 86 (Francis)
- Chopper SSA upgrade (Farrish)
- Harp to PC104 upgrade (Dela Cruz)
- Early rack documentation and space optimization (Scott)
- PSS Upgrade work (IN02BNI, B29, B30) (SSG)
- Tuesday Oct 13
Tunnel --
- Cable pulls through penetrations (EES)
- Resistor box evaluation (Coleman)
InjSB --
- BPM Work, IN02B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- Wednesday Oct 14
Tunnel --
- Cable pulls through penetrations (EES)
- Safety warden walk-through (Moser)
InjSB --
- BPM Work, IN02B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
- Safety warden walk-through (Moser)
- Conduit in penetration 135 (Electricians)
- Thursday Oct 15
Tunnel --
- S&A Level surveys
InjSB --
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- Friday Oct 16
Tunnel --
- Cable pulls through penetrations (EES)
- Mott cable removals (Scott/Riad, EES)
InjSB --
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- IN02B26 Power Lock-Out, ~915a (DC Power)
Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation
- Non-Tunnel Work
- Build new Y-chamber viewer => Y-built w/test screen, Laser being built.
- Use test screen + laser + S&A to verify position of first viewer => This week
- Install + align + vacuum seal (2) viewers => target this week
- Caryn will confirm but identified best ‘mushroom’ window, attach => done
- ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => ???
- Carlos' Wien-mania!
- Tunnel Work
- Complete remove old keV Mott cables => done
- Complete remove old gun HV cables => done
- Jim pulls Wien PS cables? => done
- Does Wien HV cable pull start? => starting this week
- Scott will finish tie back of cables on tunnel floor to cable tray => done
- Refill 86? => no, not yet
- Standing Injector Service Building Work
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, Rack re-org, IN02B22 (DC Power)
- Monday Oct 19
Tunnel --
- Cryo u-tube pulls for 0L0{2,3,4}
- Tuesday Oct 20
Tunnel --
- Cable pulls and removals
InjSB --
- BPM Work, IN0{2,3}B{*} (Francis)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- Harp to PC104 upgrade, IN03B07 (Dela Cruz)
- Early rack documentation and space optimization, IN01B{02-05} (Scott)
- PSS Upgrade, IN02{BNI, B29, B30} (SSG)
- 20A PS Install, IN02B22, 2p - 4p (DC Power)
- Wednesday Oct 21
Tunnel --
- S&A Verify line with new control
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- M56 Hardware Removal from IN02B22, (I&C)
- Thursday Oct 22
InjSB --
- Wien Magnet PS Install, IN02B22, afternoon (DC Power)
- Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Friday Oct 23
Tunnel --
- Vacuum work clean room craned in 6a - 8a (Mech Install)
- Clean room setup and prepping (Marcy)
- Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames)
- Laser room work (Shukui)
InjSB --
- Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Viewer work, IN03B07, 6a - 9a (Norris)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- 20A PS Install, IN02B22 (DC Power)
Inj Service Building Work
Time | Wed 10/21 | Thu 10/22 | Fri 10/23 |
---|---|---|---|
5a - 9a | Dela Cruz, Norris, |
Dela Cruz, Norris, |
Dela Cruz, Norris, |
9a - 12p | |
|
|
12p - 4p | DC Power, SSG, |
DC Power, SSG, Windham, |
DC Power, SSG, Windham, |
Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location
- Tunnel work
- Remove NEG filter from HV chamber ✅
- Setup mobile cleanroom over HV chamber ✅
- Vent Gun3 chamber to test Gun3 valve ✅
- Vent Gun2 chamber to test Gun2 valve ✅
- Remove 2I NEG beam line, remove NEG pedestal (temporarily) ✅
- Replace 10” flange + SHV connector + blank off + pump down ✅
- Prep Gun3 & Y-chamber for Install to remove ✅
- Wrap up UHV ion pump power supply power tests ✅
- INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 ✅
- S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) ✅
- Non-Tunnel Work
- Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve on-going
- Wien-mania! (high level schedule)
- -Wien magnetic field mapping next couple weeks
- -Bubba assembles the fixtures ✅
Injector Tunnel and Service Building Work
Location Time |
Mon 10/26 | Tue 10/27 | Wed 10/28 | Thu 10/29 | Fri 10/30 |
---|---|---|---|---|---|
InjSB 5a - 9a |
Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis | Norris, Dela Cruz, Francis |
Tunnel 5a - 9a |
Gun Vacuum Work | Gun Vacuum Work | Gun2 Table Move Y-Chamber+Gun3 Removal |
||
InjSB 9a - 12p |
Francis, SSG | Francis, Windham, SSG | Francis, Windham, SSG | Dela Cruz, Norris, Francis, SSG | Francis, SSG |
Tunnel 9a - 12p |
Gun Vacuum Work | Gun Vacuum Work | 9a CIS+MechInstall Walk-Thru | Wien Cable Pulls | Cryo 0L02 L-tube pull Fire pipe walk thru S&A Point Layouts |
InjSB 12p - 4p |
SSG | Windham, SSG | Windham, SSG Trim Rack Checks |
SSG | SSG |
Tunnel 12p - 4p |
Gun Vacuum Work | Gun Vacuum Work 3p:Videographer Tour |
S&A Point Layouts |
- Mon Oct 26
Tunnel --
- Gun vacuum work, 9a - 4p (CIS)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Viewer work, IN03B07, 6a - 9a (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- LLRF air temperature control system removal from IN01B13? (Plawski?)
- Tues Oct 27
Tunnel --
- Gun vacuum work, 9a - 3p (CIS)
- Videographer Tour, 3p+ (K. Carter + two videographers)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Viewer work, IN03B07, 6a - 9a (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
- CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- LLRF air temperature control system removal from IN01B13? (Plawski?)
- Wed Oct 28
Tunnel --
- CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
- Viewer work, IN03B07, 6a - 9a (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
- CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
- Trim Card Checks, IN02B{10+11+26} + IN04B10, 12p-1p (Richardson)
Other Possible Work....
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
- Thur Oct 29
Tunnel --
- Gun2 move, 5a - 8a (Mech Install)
- Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)
- Wien HV and control cable pulls, 9a - 1p (Dela Cruz)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
- Viewer work, IN03B07, 6a - 1p (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
Other possible work....
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
- All Hallows' Eve Eve 👻 (Fri 10/30)
Tunnel --
- Cryo L-tube Removal from 0L02, 8a - 12p (Cryo)
- Fire pipe demo job walk-through, 12p (Grames, Suhring, Renzo)
- Point Layouts, after cryo (S&A)
InjSB --
- PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
- Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
- Viewer work, IN03B07, 6a - 1p (Norris)
- BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
Other possible work....
- 20A Wien Magnet PS Install, IN02B22 (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
Week 7 (Nov 2 - Nov 6)
Fire pipe removal, viewer design, modify existing pedestals, Wien filter mapping
- Tunnel work
- Mon/Tue
- INSTALL crane support (move Y-girder, Gun3 chamber, anything else back to TL1137)
- CIS take opportunity to a) cover your stuff before fire pipe demo, b) clean up cabinets, toolbox
- EES-IC Cable Pulls, Termination, and Routing
- Wed/Thu and maybe Fri
- Fire pipe demolition
- Non-Tunnel Work
- Complete Y-chamber: add viewers, add laser vacuum window, add NEG towers, add gun valve
- Wien-mania! (high level schedule) => H/V-wien magnetic field mapping
- InjSB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
- Comm chassis to digiport server
- PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
- Viewer work, IN03B0{6+7} (Norris)
- BPM Work, IN03B{05-08, 23} (Francis)
- CIS Rack Work, IN01B{00-05} (Windham)
Other possible work...
- 20A Wien Magnet PS Install (Coleman)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
Injector Tunnel and Service Building
Location Time |
Mon 11/2 | Tue 11/3 Election Day 🇺🇸 |
Wed 11/4 | Thu 11/5 | Fri 11/6 |
---|---|---|---|---|---|
InjSB 5a - 9a |
BPM, Viewer, Wien Work | BPM, Viewer, Wien Work | BPM, Viewer, Wien Work | BPM, Viewer, Wien Work | BPM, Viewer, Wien Work |
Tunnel 5a - 9a |
Wien + viewer cable pulls INSTALL Crane Outs |
Wien + viewer cable pulls | Fire pipe demo | Fire pipe demo | F(riday) |
InjSB 9a - 12p |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
Tunnel 9a - 12p |
Wien + viewer cable pulls | Wien + viewer cable pulls | Fire pipe demo | Fire pipe demo | F(loat) |
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
Tunnel 12p - 4p |
M | T | Fire pipe demo | Fire pipe demo | F |
Week 8 (Nov 9 - Nov 13) Beamline anchors/pedestals, Wien mapping/HV system, A1/A2 cubes, prebuncher
- Tunnel work
- Tue - S&A is queued up to set new(er) gun foot pad points
- Tue/Wed - Shaun predicts 4 pedestals arrive, Jenord inspects them; other peds exist in tunnel - thank you Phil/Shaun!
- Wed/Thu/Fri - Install drills and drops anchors, prepare grout form?, maybe we return gun table (Tom, best guess for the fire pipe install?)
- ME work
- S&A drop revised points for table base pads. ECD 11/10. done
- 2I solenoid – done
- SG print full size drill template for Neil.
- Check fit of template.
- Neil – Drill holes into top of solenoid stand (existing item and is currently in place) using drill template provided by Shaun. done
- Neil drill anchor holes in floor done
- HVC table base pads. done
- Wien Girder Pedestals. done
- Aperture Girder Pedestals. done
- Details have been provided to Neil. done
- Y chamber girder
- Design new v-block mounting for Y & ion pump due to angle change of Y.
- Fabricate or modifications.
- Non-Tunnel Work
- Wien-mania! (high level schedule) - Wien magnet mapping, HVPS system controls (ADC/DAC), Switchbox build
- Complete Y-chamber build : laser window + (2) viewers + NEG Tower + Valve (gun3!?)
- A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
- Prebuncher vacuum repair, leak check
- Did the leak check braze joint happen?
- Did a final probe port length get decided?
- Can we resolve these question, repair the probe port, clean, ready for testing by Friday?
- Submit PR for PSS kicker
- ISB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos) --
- Wire HV PS
- Install Comm chassis
- PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
- Viewer upgrades, IN03B07 (Norris)
- Harp upgrades, IN03B07 (Dela Cruz)
- BPM Work, IN03B{05-08, 23} (Francis) Phase I: ✅; jump-start on Phase II ✅
- CIS Rack Work, IN01B{00-05} (Windham)
- Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
- First Aid Cabinet re-stocks, back wall behind IN02B22ish + bottom of access stairs, (Occ Med + vendor), date TBD
Injector Tunnel and Service Building
Location Time |
Mon 11/9 | Tue 11/10 | Wed 11/11 | Thu 11/12 | Fri 11/13 |
---|---|---|---|---|---|
InjSB 5a - 9a |
BPM, Viewer, Wien Work | BPM, Viewer, Wien, Harp Work | BPM, Viewer, Wien, Harp Work | BPM, Viewer, Wien, Harp Work | Viewer, Wien, Harp Work |
Tunnel 5a - 9a |
Viewer Cable Pulls | T | INSTALL Pedestals, base pads, solenoid stand drilling | INSTALL work Viewer Cable Pulls |
S&A Survey Pedestals |
InjSB 9a - 12p |
PSS Upgrade BPM, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Harp, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Harp, Viewer, Wien Work CIS Rack Work |
PSS Upgrade BPM, Harp, Viewer, Wien Work CIS Rack Work |
PSS Upgrade Harp, Viewer, Wien Work CIS Rack Work |
Tunnel 9a - 12p |
Viewer cable pulls | S&A Sets New(er) Points DC Power Resistor Box Button-Up |
INSTALL Pedestals, base pads, solenoid stand drilling | Viewer Cable Pulls 11a: Laser Safety System Audit |
S&A Survey Pedestals |
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
Tunnel 12p - 4p |
M | S&A Sets New(er) Points | Cable pulls? | R | S&A Survey Pedestals |
Week 9 (Nov 16 - Nov 20)
- Non-Tunnel Work
- Continue preparing new Y-chamber
- A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
- Prebuncher -- RF testing/tuning
- Wien-mania! (high level schedule) =>
- Review V-wien magnetic field mapping results and determine any remaining desired measurements
- Finish V-wien field mapping and move to horizontal
- Wien quad hardware arrivals?
- Install HV switcher chassis
- 200kV PSS kicker fabrication
- Tunnel work
- INSTALL grouts in pedestals (Mon/Tue) done?
- Fire pipe demo (Wed/Thur/Fri)
- ISB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
- PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
- Viewer upgrades, IN03B07 (Norris)
- Harp upgrades, IN03B07 (Dela Cruz)
- CIS Rack Work, IN01B{00-05} (Windham)
Injector Tunnel and Service Building
Location Time |
Mon 11/16 | Tue 11/17 | Wed 11/18 | Thu 11/19 | Fri 11/20 |
---|---|---|---|---|---|
InjSB 5a - 9a |
Viewer, Harp, Wien Work | Viewer, Harp, Wien Work | Viewer, Harp, Wien Work | Viewer, Harp, Wien Work | Viewer, Harp, Wien Work |
Tunnel 5a - 9a |
INSTALL Grout pedestals | T | Fire pipe demo | Fire pipe demo | Lifting Plate Load Test |
InjSB 9a - 12p |
Viewer, Harp, Wien Work CIS Rack Work |
Viewer, Harp, Wien Work CIS Rack Work |
Harp, Viewer, Wien Work CIS Rack Work |
Harp, Viewer, Wien Work CIS Rack Work |
Harp, Viewer, Wien Work CIS Rack Work |
Tunnel 9a - 12p |
INSTALL Grout pedestals | Laser room/table work Ceiling Lifting Plate Install |
Fire pipe demo | Fire pipe demo | F |
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
Tunnel 12p - 4p |
M | Laser room/table work | Fire pipe demo | Fire pipe demo | F |
Week 10 (Nov 23 - Nov 25 🦃)
- Non-Tunnel Work
- Complete assembly of new Y-chamber
- Magnetic mapping of spare aperture cube
- A1/A2 cube assemblies - (2) for vacuum testing, (1) for magnet fit-up/testing
- Prebuncher -- RF testing/tuning
- Wien-mania! (high level schedule) =>
- Horizontal Wien magnetic assembly and field mapping
- Bake V-wien electrode assembly with vacuum chamber
- V-wien HV test at UITF
- Resistor box testing at UITF?
- Tunnel work
- Opportunistic cable pulls -- who wants to do some? Good week for it.
- ISB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
- PSS Upgrades -- now at many racks, from IN01B02->IN04B14, afternoons (Beizer)
- Viewer upgrades, IN03B07 (Norris)
- Harp upgrades, IN03B07 (Dela Cruz)
- CIS Rack Work, IN01B{00-05} (Windham)
Injector Tunnel and Service Building
Location Time |
Mon 11/23 | Tue 11/24 | Wed 11/25 | Thu 🦃 11/26 | Fri 11/27 |
---|---|---|---|---|---|
InjSB 5a - 9a |
Viewer, Harp, Wien Work | Viewer, Harp, Wien Work | Viewer, Harp, Wien Work | ||
Tunnel 5a - 9a |
M | T | W | ||
InjSB 9a - 12p |
Viewer, Harp, Wien Work CIS Rack Work |
Viewer, Harp, Wien Work CIS Rack Work |
Harp, Viewer, Wien Work CIS Rack Work |
||
Tunnel 9a - 12p |
M | T | W | ||
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
||
Tunnel 12p - 4p |
M | T | W |
Week 11 (Nov 30 - Dec 4)
- Non-Tunnel Work
- H-Wien
- plate ready at shop, mic and test fit @ MMF
- order (4) Ni plates
- V-Wien
- Start HV tests @ UITF
- MHD
- complete thermal test >2.5A
- measure field profile and BL/I for CED
- DR
- measure DR per Jay's plan
- A1/A2 cubes
- complete assembly (coils + aperture), test motion and shorts
- S&A fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes)
- PSS kicker
- vendor quotes?
- place order
- Tunnel work
- Install
- Y girder + 2I solenoid from 1137 to tunnel
- Gun table to foot pads
- S&A
- Pre-align Y girder
- Pre-align gun
- PSS/CIS
- Complete laser bypass
- Align laser - test at window, viewer hole, cathode/flange
- CIS/S&A
- 2I solenoid on pedestal
- 2I vacuum connection (valve to gun)
- Final align
- Final laser check
- ISB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
- PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
- Viewer upgrades, IN03B{06-07} (Norris)
- Harp upgrades, IN03B07 (Dela Cruz)
- CIS Rack Work, IN01B{00-05} (Windham)
Injector Tunnel and Service Building
Location Time |
Mon 11/30 | Tue 12/1 | Wed 12/2 | Thu 12/3 | Fri 12/4 |
---|---|---|---|---|---|
InjSB 5a - 9a |
M | T | W | R | F |
Tunnel 5a - 9a |
M | INSTALL: Y-chamber, solenoid | PSS Laser Bypass Work | S&A: Pre-align Gun-Y | S&A: Pre-align Gun-Y |
InjSB 9a - 12p |
CIS Rack Work | CIS Rack Work | CIS Rack Work | CIS Rack Work | CIS Rack Work |
Tunnel 9a - 12p |
M | INSTALL: Y-chamber, solenoid | CIS Laser Hut Work | S&A: Pre-align Gun-Y | S&A: Pre-align Gun-Y CIS Laser Alignment Work |
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
Tunnel 12p - 4p |
M | T | W | S&A: Pre-align Gun-Y | S&A: Pre-align Gun-Y CIS Laser Alignment Work |
Week 12 (Dec 7 - Dec 11)
- Non-Tunnel Work
- Wien (Test Lab)
- Test voltage divider box, calibrating UITF Matsusada HV PSs done, opted to use FLUKE 1000:1 V-probe and RMS true-value multimeter
- U-Wien electrode alignment -- install teflon spacer (CIS) first-pass done, after discussions, may refine
- Improve V-wien electrode alignment? (S&A) deferred
- Receive Nickel endplates received, returned after finish found scratched, received again?
- A1/A2 cubes (Test Lab)
- Assemble fixture mounting plates done
- Test motion and shorts '
- Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) awaiting cubes
- Prebuncher - high power testing
- PSS kicker
- build bids received, choosing one done
- 12/9: req submitted
- MagTest
- Wrapping up A2 measurements
- Wrapping up A1 measurements
- Tunnel work
- Wien cable pulls (Dela Cruz)
- Laser alignment work (CIS) complete for this week
- Gun -> Y-chamber vacuum connections (CIS) Thursday/Friday
- Viewer cable terminations (Norris)
- ISB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz, Carlos)
- PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
- Viewer upgrades, IN03B{06-07} (Norris)
- Harp upgrades, IN03B07 (Dela Cruz)
- CIS Rack Work, IN01B{00-05} (Windham)
Injector Tunnel and Service Building
Location Time |
Mon 12/7 | Tue 12/8 | Wed 12/9 | Thu 12/10 | Fri 12/11 |
---|---|---|---|---|---|
InjSB 5a - 9a |
M | Viewer/Wien/Harp Work | Viewer/Wien/Harp Work | R | Viewer Terminations |
Tunnel 5a - 9a |
CIS Laser Work | CIS Laser Work | CIS Laser Work | S&A+CIS Drive Laser Alignment | Locking in NEG-tube BPM locations (CIS+S&A) |
InjSB 9a - 12p |
CIS Rack Work | CIS Rack Work Viewer/Wien/Harp Work |
CIS Rack Work Viewer/Wien/Harp Work |
CIS Rack Work | CIS Rack Work Viewer Terminations Wien Cabling Work |
Tunnel 9a - 12p |
CIS Laser Work | CIS Laser Work- temp Vacuum Window Install Facilities HVAC Investigation |
CIS Laser Work | S&A+CIS Drive Laser Alignment | CIS Pump Down Gun S&A Gun/Y-Chamber |
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work Viewer Terminations Wien Cabling Work |
Tunnel 12p - 4p |
CIS Laser Work | CIS Laser Work Facilities HVAC Investigation |
CIS Laser Work | S&A+CIS Drive Laser Alignment | CIS Pump Down Gun S&A Gun/Y-Chamber |
Week 13 (Dec 14 - Dec 18)
- Non-Tunnel Work
- Wien (Test Lab)
- U-Wien electrode parallelism evaluation after assembly w/teflon spacer block, spacer for hangers added (S&A) done
- Controls work continues yep
- HV PS calibration measurements, second-pass Friday
- Receive Nickel endplates? done
- A1/A2 cubes (Test Lab)
- Assembling A1/A2 cubes done
- Test motion and shorts done
- Fiducialize positions (stac5 A1=2/3/4 mm holes, manual A2=4/6/8 mm holes) (S&A) A2 done, A1 completed today
- MagTest
- Measure DR per Jay's plan continues
- QW (Wien quad) lead reinforcement and field mapping 4 done, 12 to go
- Tunnel work
- Wien cable pulls (Dela Cruz) (latter half of the week) done?
- Viewer cable terminations? (Norris) near complete
- Gun -> Y-chamber vacuum pumpdown and leak check (Stutzman, Adderley) done
- CIS Check drive laser -> cathode -> retroreflection alignment w/assembly under vacuum done
- SSG Backs out of Laser Bypass workaround in support of PSS upgrades Friday
- ISB Work
- Wien upgrade work, IN01B{00-03} (Windham, Dela Cruz)
- PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
- Viewer upgrades, IN03B{06-07} (Norris)
- Harp upgrades, IN03B07 (Dela Cruz)
- CIS Rack Work, IN01B{00-05} (Windham)
Injector Tunnel and Service Building
Location Time |
Mon 12/14 | Tue 12/15 | Wed 12/16 | Thu 12/17 | Fri 12/18 |
---|---|---|---|---|---|
InjSB 5a - 9a |
Viewer Terminations | Viewer Terminations | W | R | F |
Tunnel 5a - 9a |
CIS Vacuum Work: heating NEG chambers |
CIS Vacuum Work: Leak Checks |
Wien HV Cable Pulls? | Wien HV Cable Pulls? | F |
InjSB 9a - 12p |
CIS Rack Work Viewer Terminations |
CIS Rack Work Viewer Terminations |
CIS Rack Work | CIS Rack Work PSS Upgrades: Access Room and in Racks |
CIS Rack Work |
Tunnel 9a - 12p |
CIS Vacuum Work: heating NEG chambers |
CIS Vacuum Work: Leak Checks CIS Laser/retroreflection checks |
CIS Laser Hut Work Viewer Terminations Wien HV Cable Pulls? |
CIS Laser Hut Work Viewer Terminations |
SSG Laser Bypass Backout |
InjSB 12p - 4p |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrade CIS Rack Work |
PSS Upgrades: Access Room and in Racks CIS Rack Work |
PSS Upgrade CIS Rack Work |
Tunnel 12p - 4p |
CIS Vacuum Work | CIS Vacuum Work CIS Laser/retroreflection checks |
CIS Laser Hut Work Viewer Terminations |
CIS Laser Hut Work Viewer Terminations |
F |
Week 13.6 (Dec 21 - Dec 23)
830 toolbox meetings suspended.
Have a safe and restful winter break.
- Non-Tunnel Work
MagTest --
- DR field mapping continues
- Tunnel work
- Neutron detector field cable runs, above 0L03 (Gonzales)
- PSS upgrades -- equipment near Inj-NL gate (SSG)
- ISB Work
- CIS Rack Work, IN01B{00-05} (Windham)
- Viewer terminations, IN03B{06, 07} (Norris)
- PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere (SSG)
- Neutron detector system work, IN03+4 (Gonzales, Mock)
Week 14 (Jan 4 - Jan 8)
Happy New Year!!! 🎉🎉🎉
- AIPINJ Phase I Jobs for 2021
- Punchlist from 12/17/20 ME meeting media:AIPINJ_2021_Jobs_v3.pdf
- Non-Tunnel Work
- Wien
- V-Wien (Hernandez-Garcia)
- remove from UITF test stand
- re-assemble in Vertical orientation w/new spacers, Ni endplates, and magnet
- ~Wed deliver to S&A
- Survey of V-wien, evaluation of electrode parallelism
- Picking up new Ni endplates from machine shop, cleaning and annealing before delivery to MagTest to be used in assembly of H-wien and evaluation during field mapping (Grames)
- Fabrication of HV switcher chassis continues (Dela Cruz)
- Controls work continues (Croke)
- V-Wien (Hernandez-Garcia)
- A1/A2 Apertures
- Motor controls work continues (Windham)
- A1/A2 girder build in TL continues (Adderley)
- MagTest
- DR field mapping
- Complete QW coils lead reinforcement and mapping
- Begin H-wien field mapping?
- Tunnel work
- Prepping for Gun2 bake (Stutzman)
- Wien HV cable pulls? (Dela Cruz, Norris)
- Laser hut opto-mechanical work (Zhang)
- LCW walkthrough (CIS+I&C+MechInstall)
- ISB Work
- Wien HV cable pulls?, IN01B{00+01} (Dela Cruz, Norris)
- PSS Upgrades, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
- CIS Rack Work, IN01B{00-05} (Windham)
- Viewer upgrades, IN03B{06+07} (Norris)
- 15deg dipole interlock panel install, IN01B11 (Windham)
- iocin3 crate upgrade to VME, IN01B{04+14} (Dela Cruz)
Injector Tunnel and Service Building
Location Time |
Mon 1/4 | Tue 1/5 | Wed 1/6 | Thu 1/7 | Fri 1/8 |
---|---|---|---|---|---|
InjSB 5a - 9a |
M | T | W | R | F |
Tunnel 5a - 9a |
M | Wien HV cable pulls? | MechInstall Crane Work Wien HV cable pulls? Viewer Terminations |
Wien HV cable pulls? Viewer Terminations |
Wien HV cable pulls? Viewer Terminations |
InjSB 9a - 12p |
CIS Rack Work | CIS Rack Work -- 15deg Interlocks Panel |
CIS Rack Work iocin3 crate upgrade prep |
15deg Interlocks Panel | CIS Rack Work |
Tunnel 9a - 12p |
Gun2 Bake Preps | 9a LCW Manifold WalkThru Gun2 Bake Preps Viewer Terminations |
Gun2 Bake Preps Viewer Terminations |
Gun2 Bake Preps Viewer Terminations |
Gun2 Bake Preps Viewer Terminations |
InjSB 12p - 4p |
CIS Rack Work PSS Upgrades |
CIS Rack Work -- 15deg Interlocks Panel PSS Upgrades |
CIS Rack Work iocin3 crate upgrade prep PSS Upgrades |
15deg Interlocks Panel PSS Upgrades |
CIS Rack Work PSS Upgrades |
Tunnel 12p - 4p |
Gun2 Bake Preps | Gun2 Bake Preps | Gun2 Bake Preps | Gun2 Bake Preps | Gun2 Bake Preps |
Week 15 (Jan 11 - Jan 15)
- Non-Tunnel Work
- Wien (Hernandez-Garcia)
- Bake V-wien
- V-wien HV soak
- Fabrication of HV switcher chassis (Dela Cruz)
- A1/A2 girder build (Adderley)
- Rectify viewer air cylinder lengths? (Stutzman)
- MagTest
- DR field mapping
- Complete QW coils lead reinforcement and mapping
- Begin H-wien field mapping?
- Tunnel work
- Photocathode suitcase bake (Stutzman, Adderley)
- Wien HV cable pulls? (Dela Cruz, Norris)
- Laser hut work (Zhang)
- iocin3 job Tuesday
- Gun HV control => no problem
- Some vacuum => no problem
- Some FSD => no problem
- Insertables (viewers etc.) => no problem
- Some Pockels cell & RTP cell controls => i turned off RTP HV PS already
- Chopping aperture (not sure how current this is) => no problem
- Scraper (think this is redundant?) => do we remove now???
- Maybe some old laser controls (ocelot?) => is this really a running app???
- An application called pol_source, which has controls for a number of boards - IP Digital 24, BASIC stepper motor, IpOpto. => => what is this connected to???
- Are the remaining 4-laser apps on iocin3b? Will that mini-crate be replaced or merged? Any other apps on iocin3?
- ISB Work
- ⚡⚡⚡Power Outage⚡⚡⚡ I-BT Breaker Panel Work -- adding 50A circuit for new chopper SSA along with 225A main breaker
Details of what will lose power in ATLis 21696, Tunnel and SB racks affected - PSS Upgrades -- energizing new equipment, IN02B{NI,29,30} +briefly elsewhere, afternoons (Beizer)
- CIS Rack Work, IN01B{00-05} (Windham)
- Viewer upgrades, IN03B{06+07} (Norris)
- 15deg dipole interlock panel install, IN01B11 (Windham)
- iocin3 crate upgrade to VME, IN01B{04 + 14} (Dela Cruz)
- iocin3 will be down Monday 1/11 morning
Injector Tunnel and Service Building
Location Time |
Mon 1/11 | Tue 1/12 | Wed 1/13 | Thu 1/14 | Fri 1/15 |
---|---|---|---|---|---|
InjSB All Day |
Safing out equipment for iocin3 work | T | W | Breaker Panel Work | Float for breaker panel work |
InjSB Morning |
M | iocin3 VME upgrade 15deg interlock work |
W | Breaker Panel Work | F |
InjSB Afternoon |
PSS Upgrades | 15deg interlock work PSS Upgrades |
PSS Upgrades | Breaker Panel Work PSS Upgrades |
PSS Upgrades |
Tunnel All Day |
Suitcase bake Safing out equipment for iocin3 work |
Suitcase bake | W | Breaker Panel Work | Float for breaker panel work |
Tunnel Morning |
M | T | W | Breaker Panel Work | F |
Tunnel Afternoon |
M | T | W | Breaker Panel Work | F |
Week 16 (Jan 18 - Jan 22) Fire pipe install?
- Non-Tunnel Work--
- Tunnel work
- ISB Work
Injector Tunnel and Service Building
Location Time |
Mon 1/18 | Tue 1/19 | Wed 1/20 | Thu 1/21 | Fri 1/22 |
---|---|---|---|---|---|
InjSB 5a - 9a |
M | T | W | R | F |
Tunnel 5a - 9a |
M | T | W | R | F |
InjSB 9a - 12p |
M | T | W | R | F |
Tunnel 9a - 12p |
M | T | W | R | F |
InjSB 12p - 4p |
M | T | W | R | F |
Tunnel 12p - 4p |
M | T | W | R | F |
Penetration Work
InjSB Penetrations that are open (click for pictures): above laser hut, 58, 86, 108, 135
- 34ft from floor of InjSB to floor of Inj tunnel
- 25ft from floor of InjSB to elevated Inj tunnel cable tray
Penetration Cable Pulls/Removals --
- Tony pulling new Wien E-field HV cables
- Norris removing old Cat5 viewer cables
- Norris pulling new viewer cables
-
Riad/Scott removing old Mott HV cables -
Coleman pulling new Wien B-field magnet cables - Cole pulling new neutron detector cables (above 0L03)
-
Scott pulling motor control cables for A1++
Fire System Work
Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.
update 11/9: 25% of demo completed
update 11/23: demo completed
update 12/8: fire pipe installation in Injector slated for Winter break ~12/21 - 1/3
"The drawings needed prior to fabrication of the INJ fire pipe have not gone through the system." No fire pipe install work over winter break.
update 1/7/21: Tentative fire pipe install to occur week of 1/18 in tunnel. Should take 3-4 days, so with the holiday on Monday, likely the rest of the week.
Further fire pipe work upstairs in the service will also need 3-4 days, but won't be constant (i.e. contractor will be in and out).