Difference between revisions of "Fall SAD 2019"

From Ciswikidb
Jump to navigation Jump to search
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
 
;Summer Beam Studies
 
;Summer Beam Studies
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19541 Test large shed electrode optics]
+
*(not done) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19541 Test large shed electrode optics]
 
*Bias anode [[media:190815_life.pptx]]
 
*Bias anode [[media:190815_life.pptx]]
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19410 Bias Gun2 anode during PREX-II]
+
*(done) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19410 Bias Gun2 anode during PREX-II]
  
 
;Fall SAD Planning
 
;Fall SAD Planning
* [https://accweb.acc.jlab.org/calendar/ SAD Calendar]
+
*[https://accweb.acc.jlab.org/calendar/ SAD Calendar]
 
*[[media:190501_GunUpgradeJobs.docx]]
 
*[[media:190501_GunUpgradeJobs.docx]]
 
*[[media:30July2019_KryptonLine.pptx]]
 
*[[media:30July2019_KryptonLine.pptx]]
Line 11: Line 11:
  
 
;200 kV Gun Tasks
 
;200 kV Gun Tasks
*[http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1142 Remove small shed from UITF and prep for CEBAF]
+
*(done) [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1142 Remove small shed from UITF and prep for CEBAF]
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19616 S&A job for new small shed going into CEBAF]
+
*(done) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19616 S&A job for new small shed going into CEBAF]
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19516 Pete's BPM Atlis]
+
*(done) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19516 Pete's BPM Atlis]
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19462 Gun2 200kV cathode, 10kV anode, kr plumbing]
+
*(done) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19462 Gun2 200kV cathode, 10kV anode, kr plumbing]
 +
:[https://logbooks.jlab.org/entry/3723083 Logbook entry of 200 kV cathode assembly]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19476 CEBAF Kr Gas HV Conditioning]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19476 CEBAF Kr Gas HV Conditioning]
*[https://logbooks.jlab.org/entry/3723083 Logbook entry of 200 kV cathode assembly]
+
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19709 PM on chopper amps for 200 kV testing]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19480 Testing CEBAF w/ 200 keV beam]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19480 Testing CEBAF w/ 200 keV beam]
 +
:9/19/19 planning meeting [[media:190918_200keVbeam.docx]]
  
;SAD Tasks
+
;Injector SAD Tasks
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19463 Upgrade the loading chamber]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19463 Upgrade the loading chamber]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19465 Upgrade fiber laser connectors] [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=386979P req 1] [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=386983 req 2]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19465 Upgrade fiber laser connectors] [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=386979P req 1] [https://misportal.jlab.org/reqs/pr/viewPr.do?prNum=386983 req 2]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19633 Remove oil tank]
 
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19633 Remove oil tank]
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19690 Install 2nd decarad unit]*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19612 Remove, inspect, install FC2]
+
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19690 Install 2nd decarad unit]
 +
*(deferred) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19612 Remove, inspect, install FC2]
  
 
;PQB - SAD & CREX
 
;PQB - SAD & CREX
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19679 post-PREX II QE and AP measurements]
+
*(done) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19679 post-PREX II QE and AP measurements]
*[http://devweb.acc.jlab.org/CSUEApps/atlis/task/19669 RTP & Spot Size measurements for PREX/CREX at 240,120,30Hz]
+
*(done) [http://devweb.acc.jlab.org/CSUEApps/atlis/task/19669 RTP & Spot Size measurements for PREX/CREX at 240,120,30Hz]
 
*[http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18799 Cathode Rotation/Alignment for CREX]
 
*[http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18799 Cathode Rotation/Alignment for CREX]
 
*[http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19670 RTP/IA/Parity Settings for all 4 lasers before CREX]
 
*[http://opsweb.acc.jlab.org/CSUEApps/atlis/task/19670 RTP/IA/Parity Settings for all 4 lasers before CREX]
 
*[http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18793 RTP: Position Difference Feedback PartI to FC2/FC1 for CREX]
 
*[http://opsweb.acc.jlab.org/CSUEApps/atlis/task/18793 RTP: Position Difference Feedback PartI to FC2/FC1 for CREX]

Latest revision as of 13:45, 19 September 2019