Fall Schedule Discussion

From Ciswikidb
Revision as of 14:14, 21 June 2021 by Poelker (talk | contribs)
Jump to navigation Jump to search

We need this information to present to Andrei as our plan for the remainder of FY21 and ask for his guidance going forward.

FY21 Schedule Discussion:

  • Wastewater Irradiation Experiment Setup/Support (McCaughan)
  • Booster Assessment and Commissioning (Kazimi)
  • Booster Removal & Relocation for Injector Phase 2 Upgrade (Poelker) poelker_mccaughan UITF plans for rest of 2021
  • 200 kV Gun + Reliability (Grames)
  • Warm RF Photocathode Studies (Grames)

Please estimate the duration and resource (personnel, utility/cryogen, space) requirements for your tasks and experiments.