Difference between revisions of "February 10, 2020 - Resource meeting"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "== Announcements == * Mailing list launched => aipinj@jlab.org * Latest layout update Friday Feb 10 == Tally components by systems == ===Correctors=== == Bullets from...")
 
Line 5: Line 5:
 
== Tally components by systems ==
 
== Tally components by systems ==
  
===Correctors===
+
===Correctors (21 pairs , down from 23 pairs)===
 +
-Will re-use existing MBH (long Haimson), MHB (short Haimson), MHD (on A1 cube), and eliminate MAD in favor of another type
 +
-Total number of H/V pairs is 21 (goes down by 2 pair, so should free up 4 channels)
 +
 
 +
===Dipoles (2: same number)===
 +
-PO written for two new 15 deg dipole fits on 3" OD pipe (replaces existing similar MDS fits on 2.5" pipe)
 +
-500 keV spectrometer dipole (MBO) will either be re-used as-is, possibly modified for taller vacuum chamber aperture
 +
 
 +
===Solenoids (11: same number)===
 +
-Gun to Chopper region : retain two FG solenoids + upgrade the FH, FB, FQ with three new FX solenoids
 +
-Chopper : retain two FA solenoids captured to chopper cavities + upgrade the two FD solenoids with two new FY solenoids (TBD: one or two PS)
 +
-Chopper to Booster : upgrade FA, FL with two new FX solenoids
 +
 
 +
===Quadrupoles (6: same number)===
 +
-Replace existing 6 quads (types QW, QU) with two new triplets (3Q), under design now
 +
-If design is late or does not come to fruition, may retain the 6 quads we have now
 +
-Right now, retain one skew quad MQS0I07, but should be eliminated by improved Booster module
 +
 
 +
===Earth Coils (2: same number)===
 +
-One coil across chopper
 +
-One coil across chopper-booster
 +
 
 +
 
  
  

Revision as of 12:11, 10 February 2020

Announcements

  • Mailing list launched => aipinj@jlab.org
  • Latest layout update Friday Feb 10

Tally components by systems

Correctors (21 pairs , down from 23 pairs)

-Will re-use existing MBH (long Haimson), MHB (short Haimson), MHD (on A1 cube), and eliminate MAD in favor of another type -Total number of H/V pairs is 21 (goes down by 2 pair, so should free up 4 channels)

Dipoles (2: same number)

-PO written for two new 15 deg dipole fits on 3" OD pipe (replaces existing similar MDS fits on 2.5" pipe) -500 keV spectrometer dipole (MBO) will either be re-used as-is, possibly modified for taller vacuum chamber aperture

Solenoids (11: same number)

-Gun to Chopper region : retain two FG solenoids + upgrade the FH, FB, FQ with three new FX solenoids -Chopper : retain two FA solenoids captured to chopper cavities + upgrade the two FD solenoids with two new FY solenoids (TBD: one or two PS) -Chopper to Booster : upgrade FA, FL with two new FX solenoids

Quadrupoles (6: same number)

-Replace existing 6 quads (types QW, QU) with two new triplets (3Q), under design now -If design is late or does not come to fruition, may retain the 6 quads we have now -Right now, retain one skew quad MQS0I07, but should be eliminated by improved Booster module

Earth Coils (2: same number)

-One coil across chopper -One coil across chopper-booster





Bullets from last meeting...

  • New 200kV small shed cathode electrode at machine shop (like electron at UITF)
  • New gun 10" anode flange being designed to locate a steering coil closer to the gun
  • Phil/Marcy starting to NEG coat vacuum chambers; need a 1kW sputtering PS that works (1 kV, 1 mA)
  • PO for 200 kV injector solenoids written (delivery April - June)
  • Shaun designed alignment fixture for new beam line solenoids
  • PO for 200 kV Wien magnet coils written (delivery March)
  • Success applying +/- 20kV to UITF Wien! Testing w/ better vacuum comes next...
  • PO to be written for new 15 deg dipole next week
  • Chase assigning new names for dipole and solenoids
  • Starting to study which laser vacuum window to use 2-3/4" as-is, or 4-1/2"
  • Curt waiting on kV spec for prebuncher @ 200 kV, for Watt in S.S. cavity
  • Reza/Alicia/Dennis evaluating re-ordering of layout
  • Looking at installing valve downstream of chopper #2 this down, possibly during fc#1 repair
  • Gary Cheng inquiring about checking cryo lines between QCM and Booster
  • 5D beam line will be removed
  • Neil/Anthony working plan to build table to move QCM/Booster

ATLIS Tasks

AIPINJ

Non-AIPINJ

Quick links

Injector upgrade calendar

Run (now - May 6)
Phase 1 (May 6 - end of 2020)
Run (Jan 2021 - Sep 13 2021)
Phase 2 (Sep 13 - end of 2021)