Difference between revisions of "February 12, 2021 - PQB/RTP meeting with UVa"

From Ciswikidb
Jump to navigation Jump to search
Line 14: Line 14:
 
::- Testing RTP driver
 
::- Testing RTP driver
 
::- PQB tests during Phase 1 commissioning
 
::- PQB tests during Phase 1 commissioning
 +
 +
== Minutes and Action Items ==
 +
 +
; Riad's comment on BPM's
 +
One more thing to pay attention to: Pete had to dis-connect some BPM cables from the parity DAQ ADC boards. He moved around  some BPMs in the iocs in Injector Service Building. The cables are labelled but you will have to plug them back into the ADCs. Maybe a good time to re-organize these cables.

Revision as of 15:34, 13 February 2021

Meeting Info =

We will meet Friday Feb 12 @ 2pm via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/7572697097
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 7572697097#

Agenda

  • (Joe) - Brief upgrade status & schedule media:210210_HallD_CollaborationMeeting.pptx
  • (Shukui) - Describe modifications to laser layout, show a sketch
  • (Aaron) - Status of new RTP driver, sequence to hand off for testing, wrap this up
  • (All) - Make plans for
- Installing Pockels cell (RTP or KDP)
- Testing RTP driver
- PQB tests during Phase 1 commissioning

Minutes and Action Items

Riad's comment on BPM's
One more thing to pay attention to: Pete had to dis-connect some BPM cables from the parity DAQ ADC boards. He moved around   some BPMs in the iocs in Injector Service Building. The cables are labelled but you will have to plug them back into the ADCs. Maybe a good time to re-organize these cables.