February 22, 2021 - I&C Installation Kickoff

From Ciswikidb
Revision as of 08:00, 22 February 2021 by Grames (talk | contribs)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Meeting Info =

We will meet Monday February 22 @ 1:30 pm via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/7572697097
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 7572697097#

Agenda

Installation status
  • Schedule
    • Transition from vac/mech to girder hook-ups planned to begin April 5 (6 weeks from today)
    • We may be ready early by 1 or 2 weeks (no sooner than mid-March)
    • Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
    • Goal is HCO/System readiness for everything up to FC#2
  • Preliminary Songsheet
I&C Jobs
  • What to expect in tunnel?
    • Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2); there are 3D CAD models I can post in advance
    • Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)
  • Viewers
    • 8 total - all chromox except ITV0I02 (YAG)
    • Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
    • Crash inhibit #2 : ITV0I02 and Harp IHA0I02
  • Valves
    • 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
    • Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
    • Beam line valve - VBV1I07 (same name), same all metal gate valve
    • Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
    • All 3 valves tied to UHV vacuum fault (100 uA limit)
  • Ion pumps
  • Wien HV
    • Tony status update
  • BPMs
  • Harps
    • 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
  • Current Monitoring
    • 3 total - same as before (PCUP, A1, A2)
    • PCUP identical as before, just a new location
    • A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
    • A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
Software Jobs
  • CED
    • Michele or Gary can gives us an update
  • Apps
    • Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
    • Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
  • Screens
    • I guess many screens auto-updated from CED, that's great
    • Like with apps, will need name review; I guess system owners look at their own screens for oddities?
  • What else for software?
CIS Jobs
Plans
  • Jobs list => Phase 1 area on the upgrade home page => CEBAF Injector Upgrade
  • Will meet with Magnets, DC Power, Software next Monday Mar 4, you're welcome to join
  • When should WE meet again and leading up to April 5?
  • Then 8am and Toolbox meetings at 8:30
  • Tally ho!