Difference between revisions of "February 22, 2021 - I&C Installation Kickoff"
Jump to navigation
Jump to search
Line 15: | Line 15: | ||
*Preliminary Songsheet | *Preliminary Songsheet | ||
** Most recent posted on Friday Feb 18 | ** Most recent posted on Friday Feb 18 | ||
− | ** You can always get most recent from upgrade home page => | + | ** You can always get most recent from upgrade home page => [[CEBAF Injector Upgrade]] |
* HCO and Commissioning Jobs List | * HCO and Commissioning Jobs List | ||
** We'll go over at this this meeting | ** We'll go over at this this meeting | ||
− | ** You can always get the | + | ** You can always get to the posted lists from upgrade home page => |
; Software Jobs | ; Software Jobs | ||
* CED | * CED |
Revision as of 07:01, 22 February 2021
Meeting Info =
We will meet Monday February 22 @ 1:30 pm via BlueJeans Meeting URL (for video and/or audio call in): https://bluejeans.com/7572697097 Phone number (for audio call in): 1-888-240-2560 Meeting ID: 7572697097#
Agenda
- Installation status
- Schedule
- Transition from vac/mech to girder hook-ups planned to begin April 5 (6 weeks from today)
- We may be ready early by 1 or 2 weeks (no sooner than mid-March)
- Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
- Goal is HCO/System readiness for everything up to FC#2
- Preliminary Songsheet
- Most recent posted on Friday Feb 18
- You can always get most recent from upgrade home page => CEBAF Injector Upgrade
- HCO and Commissioning Jobs List
- We'll go over at this this meeting
- You can always get to the posted lists from upgrade home page =>
- Software Jobs
- CED
- Apps
- Screens
- I&C Jobs
- Viewers
- BPMs
- Harps
- Current Monitoring
- Valves
- Ion pumps
- Wien HV
- CIS Jobs
- This
- That
- Another
- Plans