Difference between revisions of "February 22, 2021 - I&C Installation Kickoff"

From Ciswikidb
Jump to navigation Jump to search
Line 13: Line 13:
 
**Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
 
**Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
 
**Goal is HCO/System readiness for everything up to FC#2
 
**Goal is HCO/System readiness for everything up to FC#2
 +
 
*Preliminary Songsheet
 
*Preliminary Songsheet
 
** Most recent posted on Friday Feb 18
 
** Most recent posted on Friday Feb 18
 
** Search Layout area on the upgrade home page => [[CEBAF Injector Upgrade]]
 
** Search Layout area on the upgrade home page => [[CEBAF Injector Upgrade]]
 +
 
; I&C Jobs
 
; I&C Jobs
 
* What to expect in tunnel?
 
* What to expect in tunnel?
Line 53: Line 55:
 
* CED
 
* CED
 
** Michele or Gary can gives us an update
 
** Michele or Gary can gives us an update
 +
 
* Apps
 
* Apps
 
** Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
 
** Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
 
** Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
 
** Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
 +
 
* Screens
 
* Screens
 
** I guess many screens auto-updated from CED, that's great
 
** I guess many screens auto-updated from CED, that's great
 
** Like with apps, will need name review; I guess system owners look at their own screens for oddities?
 
** Like with apps, will need name review; I guess system owners look at their own screens for oddities?
 +
 
* What else for software?
 
* What else for software?
 +
 
; CIS Jobs
 
; CIS Jobs
 
* Let's quickly scan CIS jobs, see if we missed anything [[Phase 1 - HCO & Commissioning]]
 
* Let's quickly scan CIS jobs, see if we missed anything [[Phase 1 - HCO & Commissioning]]
 +
 
; Plans
 
; Plans
 
* Jobs list => Phase 1 area on the upgrade home page => [[CEBAF Injector Upgrade]]
 
* Jobs list => Phase 1 area on the upgrade home page => [[CEBAF Injector Upgrade]]

Revision as of 08:02, 22 February 2021

Meeting Info =

We will meet Monday February 22 @ 1:30 pm via BlueJeans
Meeting URL (for video and/or audio call in): https://bluejeans.com/7572697097
Phone number (for audio call in): 1-888-240-2560
Meeting ID: 7572697097#

Agenda

Installation status
  • Schedule
    • Transition from vac/mech to girder hook-ups planned to begin April 5 (6 weeks from today)
    • We may be ready early by 1 or 2 weeks (no sooner than mid-March)
    • Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
    • Goal is HCO/System readiness for everything up to FC#2
  • Preliminary Songsheet
I&C Jobs
  • What to expect in tunnel?
    • Similar mechanical layout => Gun + 3 girders (Y + Wien + A1/A2); there are 3D CAD models I can post in advance
    • Similar utilities => LCW (A1/A2) + Air (Bubba/Phil) + Cable tray (above/below) + 3 cable drops (Y, Laser, Chopper)
  • Viewers
    • 8 total - all chromox except ITV0I02 (YAG)
    • Crash inhibit #1 : ITV0I01 and Polarized Cup IFY0I01
    • Crash inhibit #2 : ITV0I02 and Harp IHA0I02
  • Wien HV
    • Tony status update
  • BPMs
  • Harps
    • 1 total - IHA0I02 (YAG), on same cross as viewer ITV0I02 (requires crash inhibit)
  • Current Monitoring
    • 3 total - same as before (PCUP, A1, A2)
    • PCUP identical as before, just a new location
    • A1 current monitoring as before, linear bellow motion now has STAC5 motor (so remote or manual; has 3 stop positions
    • A2 current monitoring as before, linear bellows manual as before; has 3 stop positions. Used by PSS group for kicker
  • Valves
    • 3 total - all have in-line EPICS shut over ride capability (CIS installs this box)
    • Gun valve - VBV2I01A (new name), otherwise same all metal gate valve
    • Beam line valve - VBV1I07 (same name), same all metal gate valve
    • Beam line valve - VBV0I02 (same name), but now all metal gate valve, requires cable terminations like VBV1I07
    • All 3 valves tied to UHV vacuum fault (100 uA limit)
Software Jobs
  • CED
    • Michele or Gary can gives us an update
  • Apps
    • Injector steering script getting upgrades for Wien/Solenoid controls, also needs update of correctors/bpms
    • Any script that refers to CED elements from Gun to Chopper will need name review, sounds like a big job
  • Screens
    • I guess many screens auto-updated from CED, that's great
    • Like with apps, will need name review; I guess system owners look at their own screens for oddities?
  • What else for software?
CIS Jobs
Plans
  • Jobs list => Phase 1 area on the upgrade home page => CEBAF Injector Upgrade
  • Will meet with Magnets, DC Power, Software next Monday Mar 4, you're welcome to join
  • When should WE meet again and leading up to April 5?
  • Then 8am and Toolbox meetings at 8:30
  • Tally ho!