Line 9: | Line 9: | ||
; Installation status | ; Installation status | ||
* Schedule | * Schedule | ||
+ | :Transition from vac/mech to girder hook-ups planned to begin April 5 (6 weeks from today) | ||
+ | :We may be ready early by 1 or 2 weeks (no sooner than mid-March) | ||
+ | :Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30) | ||
+ | :Goal is HCO/System readiness for everything up to FC#2 | ||
* Updated songsheet | * Updated songsheet | ||
* [[Phase 1 - HCO & Commissioning]] | * [[Phase 1 - HCO & Commissioning]] |
Revision as of 06:54, 22 February 2021
Meeting Info =
We will meet Monday February 22 @ 1:30 pm via BlueJeans Meeting URL (for video and/or audio call in): https://bluejeans.com/7572697097 Phone number (for audio call in): 1-888-240-2560 Meeting ID: 7572697097#
Agenda
- Installation status
- Schedule
- Transition from vac/mech to girder hook-ups planned to begin April 5 (6 weeks from today)
- We may be ready early by 1 or 2 weeks (no sooner than mid-March)
- Total of 4 weeks are allocated for girder hook-ups (Apr 5 - Apr 30)
- Goal is HCO/System readiness for everything up to FC#2
- Updated songsheet
- Phase 1 - HCO & Commissioning
- Software Jobs
- CED
- Apps
- Screens
- I&C Jobs
- Viewers
- BPMs
- Harps
- Current Monitoring
- Valves
- Ion pumps
- Wien HV
- CIS Jobs
- This
- That
- Another
- Plans