Difference between revisions of "February 28, 2013"

From Ciswikidb
Jump to navigation Jump to search
 
Line 5: Line 5:
 
  * [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/ Arne's live link to the 12 GeV Commissioning Plan]
 
  * [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/ Arne's live link to the 12 GeV Commissioning Plan]
 
  * Commissioning Plan => [[Media:130227_Commission_Discussion.pdf]]
 
  * Commissioning Plan => [[Media:130227_Commission_Discussion.pdf]]
  * Injector Startup Plan [[Media:InjectorStartup_rev1.pdf]]
+
  * Injector Startup Plan => [[Media:InjectorStartup_rev1.pdf]]
  
 
== Mott Experiment Slide ==
 
== Mott Experiment Slide ==
 
[[File:Mott_layout.jpeg|200px|thumb|left|Annotated layout for group discussion.]]
 
[[File:Mott_layout.jpeg|200px|thumb|left|Annotated layout for group discussion.]]

Latest revision as of 10:32, 28 February 2013

EGG Meeting - ARC 428

12 GeV Commissioning Discussion

* Arne's live link to the 12 GeV Commissioning Plan
* Commissioning Plan => Media:130227_Commission_Discussion.pdf
* Injector Startup Plan => Media:InjectorStartup_rev1.pdf

Mott Experiment Slide

Annotated layout for group discussion.