===Today's Agenda===
 
===Today's Agenda===
 +
; Gun Region
 +
: Gun electrode assembly drawing w/ revised small mushroom for CEBAF [[media:ACC2003000-0310 REV A SHT 1.pdf]] [[media:ACC2003000-0310 REV A SHT 2.pdf]]
  
 
; Booster Region
 
; Booster Region
 
: Danny's present as-is layout chopper to module [[media:190207_chopper2module.pdf]]
 
: Danny's present as-is layout chopper to module [[media:190207_chopper2module.pdf]]
: Reza's present concept chopper to booster
+
: Reza's present concept chopper to booster [[media:Injector upgrade Choppers to Booster v01.pptx]]
  
===From the last meeting===
+
===From Prior Agendas ===
  
==== Gun2 electrode parts discussion [[media:190131_Gun2Electrode.pdf]] ====
+
; Gun Region
Attached is the initial electrode assembly drawing. i will update it and get info together to order
+
: Recent upgrade layout from 1/24/19 [[media:190123_gun_to_chopper.pdf]]
parts. some parts have been revised since this drawing. i would also like to show the correct electrode
+
: Slides from 1/24/19 [[media:190123_INJ.pptx]] ('''material on slide#4 is new''')
(which i presume to be the T-shaped with the small mushroom). which insulator is used? i presume
 
that one of the new top flanges we just ordered will be the top flange?
 
thanks.
 
 
 
==== From Reza for Booster layout ====
 
 
 
Hi Joe,
 
 
 
I have to miss your meeting tomorrow, been here late and we need to finish inj setup tomorrow swing. I have roughly work out lenses and buncher locations between the chopper 2  to booster:
 
 
 
1) buncher falls half way between master slit and first cell of two-cell cavity of the booster.
 
 
 
2) Present lens 5 stays where it is, right after chopper 2. Let's call distance from MSlit to lens 5 "d1".
 
 
 
3) Lens 6 is before buncher at a distance equal to "d1".
 
 
 
4) lens 7 is half way between buncher and first cell of the booster.
 
 
 
5) Spectrometer line is after the buncher.
 
 
 
I have to work out these distances with Danny and Alicia to get real numbers so we can discuss them in the meetings.
 
 
 
Once we agree on the basic structure, we can fit in other elements such as diagnostics, apertures, Fcup, pss, etc.
 
 
 
#Status of layout from Jan 24, 2019 [[media:190123_gun_to_chopper.pdf]]
 
#Slides from last [[media:190123_INJ.pptx]] ('''material on slide#4 is new''')
 

Latest revision as of 20:53, 6 February 2019

Today's Agenda

Gun Region
Gun electrode assembly drawing w/ revised small mushroom for CEBAF media:ACC2003000-0310 REV A SHT 1.pdf media:ACC2003000-0310 REV A SHT 2.pdf
Booster Region
Danny's present as-is layout chopper to module media:190207_chopper2module.pdf
Reza's present concept chopper to booster media:Injector upgrade Choppers to Booster v01.pptx

From Prior Agendas

Gun Region
Recent upgrade layout from 1/24/19 media:190123_gun_to_chopper.pdf
Slides from 1/24/19 media:190123_INJ.pptx (material on slide#4 is new)