  • Bunch charge versus frequency for different average beam currents:
BunchFreq.gif


  • Laser power needed to generate each beam current (at 532 nm and with QE=1%):
BunchLaser.gif
  • The gun bake is complete (less than 10% in pressure over 24 hours)
    • We wil activate the NEGs, followed by cool down Wednesday morning
    • Thursday we will clean up and setup for high voltage ops
    • Target day for starting HV conditioning is this Friday Nov 18
  • GTS PSS certification complete, except for the laser part