GTS meeting 12 14 20

From Ciswikidb
Revision as of 11:36, 14 December 2020 by Suleiman (talk | contribs) (Created page with "==Work plan for December - January== * Notes: ** LERF is getting its own magnet power supply. We have GTS Gun Solenoid power supply from now on. ** Xelera is in no rush to tak...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Work plan for December - January

  • Notes:
    • LERF is getting its own magnet power supply. We have GTS Gun Solenoid power supply from now on.
    • Xelera is in no rush to take back TGun. Gun will stay at JLab as long as there is use for it.
  • Plans:
    • December: re-connect beamline magnet corrector, PSS certification, re-assemble TGun enclosure
    • January: Beamline magnet racks and trim cards ON. Run 1 mA beam.
  • Beam Tests (if 1 mA run is successful):
    • TE011 cavity test
    • Vent gun HV chamber, remove Kr line, re-activate cathode, ion trapping test.