GTS meeting 1 07 19

From Ciswikidb
Revision as of 11:59, 4 January 2019 by Suleiman (talk | contribs)
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
  • List of beamline hardware modifications:
  1. Replace YAG screen on Viewer 1
  2. Replace Slit on Viewer 2 with holes assembly
  3. Replace two ion collectors with new ones
  4. Replace Harp fork (Tony)
  5. Remove modified DP can
  6. Remove Faraday Cup
  7. Remove bellow upstream of dump
  8. Install TE011 Cavity
  9. Install Deflecting Cavity
  10. Install new 5th solenoid
  11. Move DP can 1 to end of beamline
  12. All bellows at least 2.5 inch diameter


  • List of software and controls changes:
  1. Re-program SCAM to allow for 1 Hz and 50 ns pulses
  2. Add 5th solenoid to magnet screen