(Created page with "= '''List of completed beamline hardware modifications''' = # Replace YAG screen on Viewer 1 # Replace Slit on Viewer 2 with holes assembly # Replace two ion collectors with...")
 
Line 27: Line 27:
  
  
= ''' Re-install gain-switched laser (seed and pre-amp) from GTS to LERF''' =
+
= ''' Re-install gain-switched laser (seed and pre-amp) in GTS''' =

Revision as of 18:41, 9 February 2019

List of completed beamline hardware modifications

  1. Replace YAG screen on Viewer 1
  2. Replace Slit on Viewer 2 with holes assembly
  3. Replace two ion collectors with new ones
  4. Replace Harp fork (Tony)
  5. Remove modified DP can
  6. Remove Faraday Cup
  7. Remove bellow upstream of dump
  8. Remove LDR Harp arm and replace with ion-pump
  9. Rotate Viewer 3 to vertical
  10. Install TE011 Cavity
  11. Install Deflecting Cavity
  12. Install new 5th solenoid
  13. Move DP can 1 to end of beamline
  14. All bellows at least 2.5 inch diameter
  15. Both gate valves are 2.5 inch-bore and will remain on beamline
  16. S&A on Thursday February 7, 2019

List of hardware support

  1. Install Deflecting Cavity power supply, MO and other parts
  2. Install TE011 Cavity readout cable and electronics


List of software and controls changes

  1. Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
  2. Add 5th solenoid to magnet screen


Re-install gain-switched laser (seed and pre-amp) in GTS