GTS meeting 2 18 19
Jump to navigation
Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
No Beam Tasks
- Re-install Viewer 3 camera
- Calibrate Viewers
- Install laser seed and pre-amp (frequency = 499.000 MHz)
- Turn on QW Deflecting cavity
Commissioning at 125 kV with VL Beam and 90-min Sb on GaAs substrate
- Check viewers
- Check magnets
- Check Harp
- Check QW Deflecting cavity
- Measure bunch length with QWD cavity
- Check 1-D pepper-pot
Commissioning at 125 kV with Tune Beam
- Measure beam emittance with Harp
- Measure beam emittance with 1-D pepper-pot
- Measure bunch length with QWD cavity
Commissioning at 125 kV with CW Beam
- Deliver 100 uA to dump
- Check TE011 cavity signal