* Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias.
+
* Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias. This is to be compared to QE ~ 3.9% in Prep Chamber with -280 V bias before moving the photocathode to Gun.
  
* Gun vacuum improved when opeening the gate valve to beamline – beamline vacuum went higher.
+
* Gun vacuum improved when opening the gate valve to beamline
  
 
* Beam to F-Cup
 
* Beam to F-Cup
  
 
* Plan to complete the second part of beamline in two weeks. We will have one-week down in about 2 weeks to install the second DP can, solenoid, ion precipitator and the BNNT diagnostic station.
 
* Plan to complete the second part of beamline in two weeks. We will have one-week down in about 2 weeks to install the second DP can, solenoid, ion precipitator and the BNNT diagnostic station.

Latest revision as of 12:55, 7 March 2017

  • Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias. This is to be compared to QE ~ 3.9% in Prep Chamber with -280 V bias before moving the photocathode to Gun.
  • Gun vacuum improved when opening the gate valve to beamline
  • Beam to F-Cup