  • Laser 10 W Fiber Amp will be moved to Hall A Compton on April 8, 2019


  • List of things to do:
  1. Calibrate new DQWR RF power supply up to 500 W
  2. Measure bunch length using new RF supply
  3. Transverse beam emittance measurement with 1D pepper-pot
  4. Commission TE011 cavity
  5. Radiation Surveys at 1 mA
  6. Measure Drift Emittance at 200 and 300 kV and laser rms = 0.9 mm
  7. Ghost beam studies with P-Gun