Difference between revisions of "GTS meeting 4 04 17"

From Ciswikidb
Jump to navigation Jump to search
Line 4: Line 4:
 
# Change laser size: x2 and x0.5
 
# Change laser size: x2 and x0.5
 
# Calibrate laser power meter at exit window vs input window - Done
 
# Calibrate laser power meter at exit window vs input window - Done
# Degas Faraday Cup
+
# Degas Faraday Cup - ''Done''
 
# Grow new photocathode with full active area - delayed to next week, will run first with existing limited active area photocathode
 
# Grow new photocathode with full active area - delayed to next week, will run first with existing limited active area photocathode
 
# Beamline bake - Done
 
# Beamline bake - Done
 
# Remove old laser - Done
 
# Remove old laser - Done
 
# Put ND filters in front of YAG Screen cameras to prevent camera saturation - Done
 
# Put ND filters in front of YAG Screen cameras to prevent camera saturation - Done

Revision as of 17:24, 10 April 2017

  • Plans for this week:
  1. Laser spot walk to make sure spot is round and no clipping
  2. Measure laser size versus laser power - Done
  3. Change laser size: x2 and x0.5
  4. Calibrate laser power meter at exit window vs input window - Done
  5. Degas Faraday Cup - Done
  6. Grow new photocathode with full active area - delayed to next week, will run first with existing limited active area photocathode
  7. Beamline bake - Done
  8. Remove old laser - Done
  9. Put ND filters in front of YAG Screen cameras to prevent camera saturation - Done