Difference between revisions of "GTS meeting 4 22 19"

From Ciswikidb
Jump to navigation Jump to search
 
(3 intermediate revisions by 2 users not shown)
Line 1: Line 1:
* Remove P-Gun:
+
* Disconnect P-Gun from beamline
**
+
* Install T-Gun
**
 
 
 
 
 
* Install T-Gun:
 
**
 
 
** Modify wall-plug of new Spellman HV power supply (150 kV, 67 mA, 10 kW)
 
** Modify wall-plug of new Spellman HV power supply (150 kV, 67 mA, 10 kW)
  
  
 
* Update SCAM firmware - lower frequencies (0.5 Hz) and shorter pulses (50 ns) for Free Run Mode
 
* Update SCAM firmware - lower frequencies (0.5 Hz) and shorter pulses (50 ns) for Free Run Mode

Latest revision as of 10:52, 1 May 2019

  • Disconnect P-Gun from beamline
  • Install T-Gun
    • Modify wall-plug of new Spellman HV power supply (150 kV, 67 mA, 10 kW)


  • Update SCAM firmware - lower frequencies (0.5 Hz) and shorter pulses (50 ns) for Free Run Mode