  • ATLis Tasks:
  1. Remove GTS Photogun and its Preparation Chamber to be ready to install Thermionic Gun [1]
  2. Install New Spellman HV Supply at GTS (150 kV, 67 mA) [2]
  3. Update SCAM firmware - lower frequencies (0.5 Hz) and shorter pulses (50 ns) for Free Run Mode [3]


  • TOSP:
  1. Operation of Thermionic Gun Hot Deck