Difference between revisions of "GTS meeting 7 22 19"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "* Progress: ** HV supply installed, with remote operation-completed ** Macro pulsing wiring- completed ** Fiber-optic communications wired and functioning- completed ** Gun in...")
 
 
(One intermediate revision by the same user not shown)
Line 1: Line 1:
* Progress:
+
* Progress: [https://logbooks/entry/3708353]
** HV supply installed, with remote operation-completed
 
** Macro pulsing wiring- completed
 
** Fiber-optic communications wired and functioning- completed
 
** Gun installed with Josh's spool- completed
 
** Hot deck constructed and installed -completed
 
** RF transmission line constructed and installed- completed
 
** Troubleshooting DC voltages on hot deck- completed
 
** Gun under vacuum removal turbo- completed
 
 
 
 
 
* Remaining Tasks:
 
** Cathode activation- waiting on Karl's instruction
 
** HV processing- needs to be after cathode activation
 
** RF/macro pulsing troubleshooting- need scope and power meter
 
** Survey and alignment- need to scheduled
 
** Hot Deck OSP
 
** Fiber-plastic corona cover
 
 
 
 
 
* Schedule:
 
** RF troubleshooting as soon as I have required equipment. Start today?
 
** Cathode activation- as soon as I get the required settings from Karl it will be completed the same day.
 
** HV processing (with cover and RadMon)- the day after cathode activation.
 
** survey and alignment- ideally Friday 7/19/19
 

Latest revision as of 09:33, 23 July 2019